November 30, 2018 Update: Due to this email from the Massachusetts Department of Energy Resources (DOER) on October 12, 2018, SRECTrade had been operating under the premise that facilities larger than 25 kW DC could submit their SQA and mechanically complete documentation “by no later than December 10, 2018”. It has been brought to our attention that the mechanically complete extension applications for facilities larger than 25 kW DC had to have submitted an SQA application by November 26, 2018.
The December 10th deadline is for the mechanically complete document to be added to the existing SQA.
SRECTrade recommends that all affected facilities submit their SMART Initial Application Period applications by 11:59pm ET tonight, November 30th.
On Friday, October 12th, the Massachusetts Department of Energy Resources (DOER) announced that the Solar Massachusetts Renewable Target (SMART) Program effective date is November 26, 2018. November 26th is now the deadline for facilities larger than 25 kW DC to become mechanically complete and for facilities smaller than or equal to 25 kW DC to receive their Permission to Operate (PTO). On November 26th, at 12:00pm ET, the SMART Statement of Qualification application portal will open to begin accepting Statement of Qualification Applications for prospective Solar Tariff Generation Units (“STGU”) seeking to qualify under SMART.
Facilities larger than 25 kW DC will have until December 10, 2018 to submit their documentation demonstrating mechanical completion. Once granted, mechanically complete extensions are indefinite; facilities should simply submit their Permission to Operate (PTO) documents once received to complete their statement of qualification application. As a reminder, facilities can demonstrate mechanical completion by submitting one of the following documents:
- Certificate of Completion
- Proof that a wiring inspection has been scheduled by a date shortly after November 26, 2018
- Affidavit signed by engineer of record stating that project is “mechanically complete”
- Other documentation deemed satisfactory by DOER
Facilities smaller than or equal to 25 kW DC will have until February 15, 2019 to submit an application demonstrating authorization to interconnect. In other words, the PTO must be dated on or before November 26, 2018, but the DOER application can be submitted up through February 15, 2019.
Please note that SRECTrade typically asks for complete applications to be received five (5) business days in advance in order to guarantee submission by the DOER deadline.