Solar Capacity in the SREC States – October 2011

Posted October 27th, 2011 by SRECTrade.

SRECTrade SREC Markets Report: October 2011

The following post outlines the megawatts of solar capacity certified and/or registered to create SRECs in the Solar REC markets SRECTrade currently serves.

A PDF copy of this table can be found here.

Capacity_October2011 (1)

PJM Eligible Systems

As of the end of October, there were 19,403 solar PV and 252 solar thermal systems registered and eligible to create SRECs in the PJM Generation Attribute Tracking System (GATS) registry. Of these eligible systems, 83 (0.42%) have a nameplate capacity of 1 megawatt or greater, of which only 6 systems are greater than 5 MW. The largest system, currently located in New Jersey, is 18.3 MW, and the second largest, located in Ohio is 12 MW. The third largest system, at 11.2 MW, is located in Delaware.

Delaware: The reporting year 2011-2012 requirement for DE equates to approximately 23,340 SRECs being retired. If all retired SRECs were of DE2011-2012 vintage, approximately 19.5 MW would need to be operational all year long. As of October 24, 2011, 22.7 MW of solar capacity was registered and eligible to create DE SRECs in PJM GATS. 11.2 MW of the 22.7 MW currently eligible is from the Dover Sun Park project developed by LS Power. In the 2011-12 compliance year, Delmarva Power has contracted to purchase 9,846 SRECs from the project, of which 7,000 are being held by the Sustainable Energy Utility (SEU) until 2015-16*. As of this writing, PJM GATS reported the issuance of 6,677 DE2011-2012 SRECs. Additional SRECs from the DE2010-2011 period may also impact the market should there be a demand for these older vintage SRECs.

Maryland: Maryland’s 2011 Solar RPS target requires approximately 32,240 SRECs to be retired. To meet this using only 2011 vintage SRECs, approximately 26.9 MW would need to be operational all year long. As of October 24, 2011, 52 MW of solar capacity was registered to create MD eligible SRECs. 30.8 MW of this capacity was sited in the state of MD. The RPS currently requires electricity suppliers to acquire SRECs from in-state sited solar systems before looking to outside systems. As of this writing, PJM GATS reported the issuance of 19,653 MD2011 SRECs from MD sited systems. There are also MD sited SRECs available from 2010, which could be utilized for compliance needs in 2011.

MD Chart

New Jersey: The New Jersey 2012 reporting year requires 442,000 SRECs to be retired. This equates to approximately 368 MW of capacity being operational all year long. Given the demand for NJ2011 Solar RECs, older vintage SRECs will not impact the 2012 market. As of October 24, 2011, 412.8 MW of solar capacity was registered and eligible to create NJ SRECs in PJM GATS. While this figure represents all projects registered in GATS, there are recently installed projects awaiting issuance of a New Jersey state certification number. This delay results in a portion of installed projects not yet represented in the 412.8 MW figure. As of August 31, 2011 the NJ Office of Clean Energy (NJ OCE) reported that 430.4 MW of solar had been installed in NJ. For more details on the increase in NJ capacity see this post. As of this writing, PJM GATS reported the issuance of 129,441 NJ2012 SRECs.

NJ Chart

Ohio: Ohio’s 2011 RPS solar target requires approximately 45,210 SRECs to be retired by the end of the compliance period. At least 50% of the SREC requirement must come from systems sited in the state. As of October 24, 2011, 27.4 MW of in-state capacity and 54.5 MW of out-of-state capacity were eligible to generate OH SRECs. Additionally, for the year to date, GATS has issued 21,137 in-state and 41,228 out-of-state OH2011 eligible SRECs. Additional SRECs from prior years are also eligible for the current compliance period, which may impact the current year’s requirements.

Pennsylvania: The reporting year 2012 requirement for PA equates to retiring approximately 48,430 eligible SRECs. If all compliance obligations were met using 2012 vintage SRECs, approximately 41.9 MW would need to be operational all year long. As of October 24, 2011, 146.4 MW of solar capacity was registered and eligible to create PA compliant SRECs. As of this writing, PJM GATS reported the issuance of 50,512 PA2012 SRECs. Given the oversupply during previous reporting years, there are also PA2012 eligible SRECs from the 2010 and 2011 reporting years.

Washington, DC: The Council of the District of Columbia and the city’s Mayor signed into law the Distributed Generation Amendment Act of 2011. The amendment increases the RPS solar requirements and closes the district’s boarders from out of district sited systems. The figures displayed above demonstrate the capacity of systems eligible to create DC SRECs moving forward. These figures do not take into consideration the amount of electricity delivered into the district that may be exempt from complying with the increases given some electricity contracts may have been signed prior to the amendment’s implementation. According to GATS, 16,744 DC2011 SRECs have been issued for the year to date. Some SRECs issued in the 2010 compliance period may also be available and can be used to meet the 2011 RPS solar requirements.

Massachusetts DOER Qualified Projects

As of October 24, 2011, there were 1,015 MA DOER qualified solar projects; 991 operational and 24 not operational. Of these qualified systems, 11 (1.1%) have a nameplate capacity of 1 megawatt or greater, of which only 3 are between 1.5 and 2 MW. Three of the projects greater than 1 MW are currently operational. Electricity suppliers providing power to the state need to acquire approximately 62,900 SRECs in 2011. Through the Q2 2011 issuance period (10/15/11), 9,499 SRECs have been minted. The Department of Energy Resources (DOER) projects approximately 29,000 SRECs to be generated this year, leaving the market short approximately 33,900 SRECs.

Capacity Summary By State

The tables above demonstrate the capacity breakout by state. Note, that for all PJM GATS registered projects, each state includes all projects certified to sell into that state. State RPS programs that allow for systems sited in other states to participate have been broken up by systems sited in-state and out-of-state. Additional detail has been provided to demonstrate the total capacity of systems only certified for one specific state market versus being certified for multiple state markets. For example, PA includes projects only certified to sell into the PA SREC market, broken out by in state and out of state systems, as well as projects that are also certified to sell into PA and Other State markets broken out by in state and out of state systems (i.e. OH, DC, MD, DE, NJ). PA Out of State includes systems sited in states with their own state SREC market (i.e. DE) as well as systems sited in states that have no SREC market (i.e. VA). Also, it is important to note that the Current Capacity represents the total megawatts eligible to produce and sell SRECs as of the noted date, while the Estimated Required Capacity – Current and Next Reporting Year represents the estimated number of MW that need to be online on average throughout the reporting period to meet the RPS requirement within each state. For example, New Jersey needs approximately 368 MW online for the entire 2012 reporting year to meet the RPS requirement. Additionally, the data presented above does not include projects that are in the pipeline or currently going through the registration process in each state program. This data represents specifically the projects that have been approved for the corresponding state SREC markets as of the dates noted.

*Source: State of Delaware Pilot Program For the Procurement of Solar Renewable Energy Credits: Recommendations of the Renewable Energy Taskforce

Note: SREC requirements for markets without fixed SREC targets have been forecast based based on EIA Report “By End-Use Sector, by State, by Provider”. Projected SRECs required utilizes the most recent EIA electricity data applying an average 1.5% growth rate per forecast year. The state’s RPS Solar requirement is then multiplied by forecast total electricity sales to arrive at projected SRECs required. Projected capacity required is based on a factor of 1,200 MWh in PJM states and 1,130 MWh in MA, generated per MW of installed capacity per year.

MA Capacity Update

Posted October 6th, 2011 by SRECTrade.

The MA Department of Energy Resources (DOER) recently published an updated qualified solar projects list as of September 23, 2011. The state currently has a total of 982 solar projects, 957 operational and 25 not operational, eligible for the SREC program. 11 of the 982 projects are greater than 1 MW, 3 of which are currently operational. The largest project, located in Sheffield, MA and approximately 2.0 MW, is not yet operational. The second largest project is 1.8 MW, located in Dartmouth, MA, and has been operational since March 2011. The table below demonstrates the change in capacity and # of projects from the last update on August 15, 2011.


8/15/11 9/23/11 Change % Change
Capacity (MW)
Operational 23.0 26.6 3.7 15.9%
Not Operational1 14.9 14.0 (1.0) -6.6%
Total 37.9 40.6 2.7 7.0%
Projects (#)
Operational 829 957 128 15.4%
Not Operational1 32 25 (7) -21.9%
Total 861 982 121 14.1%
1. A decline in capacity and # of projcts can be explained by not operational projects converting to operational.

Overall, the total qualified capacity currently stands at 40.6 MW, of which 26.6 MW is operational. The next SREC issuance period is scheduled for October 15, 2011. This will cover all SRECs generated during Q2 2011. Based on the information provided by the DOER as of 9/12/2011, 2,358 SRECs were issued in Q1 2011 (issuance date was 7/15/11). Additionally, based on the data provided, 5,652* MWh have been reported to the MassCEC Production Tracking System (PTS) for the period covering April – June 2011. An another 3,929* MWh have been reported during July and August 2011.

Taking into consideration the estimated load exemptions for the TransCanada settlement, MA electricity suppliers need to acquire approximately 63,000 SRECs during the 2011 compliance year.  According to the DOER 2012 minimum standard announcement, the forecast generation for the 2011 compliance year is 29,056 SRECs.

The chart below demonstrates the qualified capacity as of 9/23/11 compared to the estimated MW requirements needed to be online and operational during the entire 2011 and 2012 compliance years to meet the state’s solar obligations.

MA Capacity 9_23_11

Note: The 2011 and 2012 estimated megawatts required in the chart above have been adjusted for the impact of the TransCanada settlement.

* These figures represent the MWhs reported to PTS on a monthly basis. The DOER notes that the data from PTS is not finalized and the actual number of SRECs minted by NEPOOL GIS may differ.


Solar Capacity in the SREC States – September 2011

Posted September 26th, 2011 by SRECTrade.

SRECTrade SREC Markets Report: September 2011

The following post outlines the megawatts of solar capacity certified and/or registered to create SRECs in the SREC markets SRECTrade currently serves.

For a PDF copy of this table click here.

Capacity_September2011

PJM Eligible Systems

As of the end of September, there were 18,822 solar PV (18,571) and solar thermal (251) systems registered and eligible to create SRECs in the PJM Generation Attribute Tracking System (GATS) registry. Of these eligible systems, 81 (0.43%) have a nameplate capacity of 1 megawatt or greater, of which only 6 systems are greater than 5 MW. The largest system, currently located in New Jersey, is 18.3 MW, and the second largest, located in Ohio is 12 MW. The third largest system, at 11.2 MW, is located in Delaware.

Beginning of energy year for DE, NJ, and PA

June 1, 2011 marked the beginning of the new energy year for DE, NJ, and PA. All requirements for these markets increase given their RPS solar carve out schedules. SRECs for the month of August, the third creation period for the new reporting year, will be minted at the end of September.

Delaware: The reporting year 2011-2012 requirement for DE equates to approximately 21 MW being online for the entire year or approximately 25,600 SRECs created. As of September 25, 2011, 20.8 MW of solar capacity was registered and eligible to create DE SRECs in PJM GATS. 11.2 MW of the 20.8 MW currently eligible is from the Dover Sun Park project developed by LS Power. In the 2011-12 compliance year, Delmarva Power has contracted to purchase 9,846 SRECs from the project, of which 7,000 are being held by the Sustainable Energy Utility (SEU) until 2015-16*.

New Jersey: The reporting year 2012 requirement for NJ equates to approximately 368 MW being online for the entire year with a fixed SREC requirement of 442,000 MWhs. As of September 25, 2011, 397.1 MW of solar capacity was registered and eligible to create NJ SRECs in PJM GATS. While this figure represents all projects registered in GATS, there are recently installed projects awaiting issuance of a New Jersey state certification number. This delay results in a portion of installed projects not yet represented in the 397.1 MW figure. As of July 31, 2011 the NJ Office of Clean Energy (NJ OCE) reported that 399.9 MW of solar had been installed in NJ. For more details on the increase in NJ capacity see this post.

Pennsylvania: The reporting year 2012 requirement for PA equates to approximately 44 MW being online for the entire year or approximately 53,000 SRECs created. As of September 25, 2011, 133.4 MW of solar capacity was registered and eligible to create PA eligible SRECs.

Washington, D.C. – Distributed Generation Amendment Act of 2011 Implemented

The Council of the District of Columbia and the city’s Mayor signed into law the Distributed Generation Amendment Act of 2011. The amendment increases the RPS solar requirements and closes the district’s boarders from out of district sited systems. The figures displayed above demonstrate the capacity of systems eligible to create DC SRECs moving forward.

Massachusetts DOER Qualified Projects

As of August 15, 2011, there were 861 MA DOER qualified solar projects; 829 operational and 32 not operational. Of these qualified systems, 11 (1.3%) have a nameplate capacity of 1 megawatt or greater, of which only 3 are between 1.5 and 2 MW. Three of the projects greater than 1 MW are currently operational.

Capacity Summary By State

The tables above demonstrate the capacity breakout by state. Note, that for all PJM GATS registered projects, each state includes all projects certified to sell into that state. State RPS programs that allow for systems sited in other states to participate have been broken up by systems sited in state and out of state. Additional detail has been provided to demonstrate the total capacity of systems only certified for one specific state market versus being certified for multiple state markets. For example, PA includes projects only certified to sell into the PA SREC market, broken out by in state and out of state systems, as well as projects that are also certified to sell into PA and Other State markets broken out by in state and out of state systems (i.e. OH, DC, MD, DE, NJ). PA Out of State includes systems sited in states with their own state SREC market (i.e. DE) as well as systems sited in states that have no SREC market (i.e. VA). Also, it is important to note that the Current Capacity represents the total megawatts eligible to produce and sell SRECs as of the noted date, while the Estimated Required Capacity – Current and Next Reporting Year represents the estimated number of MW that need to be online on average throughout the reporting period to meet the RPS requirement within each state. For example, New Jersey needs approximately 368 MW online for the entire 2012 reporting year to meet the RPS requirement. Additionally, the data presented above does not include projects that are in the pipeline or currently going through the registration process in each state program. This data represents specifically the projects that have been approved for the corresponding state SREC markets as of the dates noted.

*Source: State of Delaware Pilot Program For the Procurement of Solar Renewable Energy Credits: Recommendations of the Renewable Energy Taskforce

Solar Capacity in the SREC States – August 2011

Posted August 26th, 2011 by SRECTrade.

SRECTrade SREC Markets Report: August 2011

The following post outlines the megawatts of solar capacity certified and/or registered to create SRECs in the SREC markets SRECTrade currently serves.

For a PDF copy of this table click here.

Renewable Generators in GATS 8_25_11_v4

PJM Eligible Systems

As of the end of August, there were 18,112 solar PV (17,791) and solar thermal (321) systems registered and eligible to create SRECs in the PJM Generation Attribute Tracking System (GATS) registry. Of these eligible systems, 77 (0.43%) have a nameplate capacity of 1 megawatt or greater, of which only 6 systems are greater than 5 MW. The largest system, currently located in New Jersey, is 18.3 MW, and the second largest, located in Ohio is 12 MW. The third largest system, at 11.2 MW, is located in Delaware.

Beginning of energy year for DE, NJ, and PA

June 1, 2011 marked the beginning of the new energy year for DE, NJ, and PA. All requirements for these markets increase given their RPS solar carve out schedules. SRECs for the month of July, the second creation period for the new reporting year, will be minted at the end of August.

Delaware: The reporting year 2011-2012 requirement for DE equates to approximately 21 MW being online for the entire year or approximately 25,600 SRECs created. As of August 25, 2011, 20.5 MW of solar capacity was registered and eligible to create DE SRECs in PJM GATS. 11.2 MW of the 20.5 MW currently eligible is from the Dover Sun Park project developed by LS Power. In the 2011-12 compliance year, Delmarva Power has contracted to purchase 9,846 SRECs from the project, of which 7,000 are being held by the Sustainable Energy Utility (SEU) until 2015-16*.

New Jersey: The reporting year 2012 requirement for NJ equates to approximately 368 MW being online for the entire year with a fixed SREC requirement of 442,000 MWhs. As of August 25, 2011, 379 MW of solar capacity was registered and eligible to create NJ SRECs in PJM GATS. While this figure represents all projects registered in GATS, there are recently installed projects awaiting issuance of a New Jersey state certification number. This delay results in a portion of installed projects not yet represented in the 379 MW figure. On July 26, 2011 the NJ Office of Clean Energy (NJ OCE) reported that as of June 30, 2011 more than 380 MW (10,086 projects) of solar had been installed in NJ. The news release noted that 40 MW were installed in the month of June. The installation data for July 2011 has not yet been released by the NJ OCE. For more details on the the current NJ market conditions see this post.

Pennsylvania: The reporting year 2012 requirement for PA equates to approximately 44 MW being online for the entire year or approximately 53,000 SRECs created. As of August 25, 2011, 124.5 MW of solar capacity was registered and eligible to create PA SRECs in PJM GATS.

Massachusetts DOER Qualified Projects

As of August 15, 2011, there were 861 MA DOER qualified solar projects; 829 operational and 32 not operational. Of these qualified systems, 11 (1.3%) have a nameplate capacity of 1 megawatt or greater, of which only 3 are between 1.5 and 2 MW. Three of the projects greater than 1 MW are currently operational.

Capacity Summary By State

The tables above demonstrate the capacity breakout by state. Note, that for all PJM GATS registered projects, each state includes all projects certified to sell into that state. State RPS programs that allow for systems sited in other states to participate have been broken up by systems sited in state and out of state. Additional detail has been provided to demonstrate the total capacity of systems only certified for one specific state market versus being certified for multiple state markets. For example, PA includes projects only certified to sell into the PA SREC market, broken out by in state and out of state systems, as well as projects that are also certified to sell into PA and Other State markets broken out by in state and out of state systems (i.e. OH, DC, MD, DE, NJ). PA Out of State includes systems sited in states with their own state SREC market (i.e. DE) as well as systems sited in states that have no SREC market (i.e. VA). Also, it is important to note that the Current Capacity represents the total megawatts eligible to produce and sell SRECs as of the noted date, while the Estimated Required Capacity – Current and Next Reporting Year represents the estimated number of MW that need to be online on average throughout the reporting period to meet the RPS requirement within each state. For example, New Jersey needs approximately 368 MW online for the entire 2012 reporting year to meet the RPS requirement. Additionally, the data presented above does not include projects that are in the pipeline or currently going through the registration process in each state program. This data represents specifically the projects that have been approved for the corresponding state SREC markets as of the dates noted.

*Source: State of Delaware Pilot Program For the Procurement of Solar Renewable Energy Credits: Recommendations of the Renewable Energy Taskforce

Solar Capacity in the SREC States – July 2011

Posted July 26th, 2011 by SRECTrade.

SRECTrade SREC Markets Report: July 2011

The following post outlines the megawatts of solar capacity certified and/or registered to create SRECs in the SREC markets SRECTrade currently serves.

For a PDF copy of this table click here.

Capacity_July11

PJM Eligible Systems

As of the end of July, there were 17,106 solar PV (16,792) and solar thermal (314) systems registered and eligible to create SRECs in the PJM Generation Attribute Tracking System (GATS) registry. Of these eligible systems, 70 (0.40%) have a nameplate capacity of 1 megawatt or greater, of which only 4 systems are greater than 5 MW. The largest system, currently located in New Jersey, is 18.3 MW, and the second largest, located in Ohio is 12 MW. The third largest system, at 10 MW, is located in IL and eligible for the MD, PA, and DC SREC markets. The fourth largest, at 6.2 MW, is located in New Jersey.

New Energy Year To Begin for DE, NJ, and PA

June 1, 2011 marks the beginning of the new energy year for DE, NJ, and PA. All requirements for these markets increase given their RPS solar carve out schedules. SRECs for the month of June, the first creation period for the new reporting year, will be minted at the end of July.

Delaware: The reporting year 2011-2012 requirement for DE equates to approximately 21 MW being online for the entire year or approximately 25,600 SRECs created. As of July 25, 2011, 9.1 MW of solar capacity was registered and eligible to create DE SRECs in PJM GATS.

New Jersey: The reporting year 2012 requirement for NJ equates to approximately 368 MW being online for the entire year with a fixed SREC requirement of 442,000 MWhs. As of July 25, 2011, 347.5 MW of solar capacity was registered and eligible to create NJ SRECs in PJM GATS. While this figure represents all projects registered in GATS, there are recently installed projects awaiting issuance of a New Jersey state certification number. This delay results in a portion of installed projects not yet represented in the 347.5 MW figure. On July 26, 2011 the NJ Office of Clean Energy (NJ OCE) reported that as of June 30, 2011 more than 380 MW (10,086 projects) of solar had been installed in NJ. The news release noted that 40 MW were installed in the month of June.

Pennsylvania: The reporting year 2012 requirement for PA equates to approximately 44 MW being online for the entire year or approximately 53,000 SRECs created. As of July 25, 2011, 115.7 MW of solar capacity was registered and eligible to create PA SRECs in PJM GATS.

Massachusetts DOER Qualified Projects

As of July 11, 2011, there were 682 MA DOER qualified solar projects; 649 operational and 33 not operational. Of these qualified systems, 11 (1.6%) have a nameplate capacity of 1 megawatt or greater, of which only 3 are between 1.5 and 2 MW. Three of the projects greater than 1 MW are currently operational.

Capacity Summary By State

The tables above demonstrate the capacity breakout by state. Note, that for all PJM GATS registered projects, each state includes all projects certified to sell into that state. State RPS programs that allow for systems sited in other states to participate have been broken up by systems sited in state and out of state. Additional detail has been provided to demonstrate the total capacity of systems only certified for one specific state market versus being certified for multiple state markets. For example, PA includes projects only certified to sell into the PA SREC market, broken out by in state and out of state systems, as well as projects that are also certified to sell into PA and Other State markets broken out by in state and out of state systems (i.e. OH, DC, MD, DE, NJ). PA Out of State includes systems sited in states with their own state SREC market (i.e. DE) as well as systems sited in states that have no SREC market (i.e. VA). Also, it is important to note that the Current Capacity represents the total megawatts eligible to produce and sell SRECs as of the noted date, while the Estimated Required Capacity – Current and Next Reporting Year represents the estimated number of MW that need to be online on average throughout the reporting period to meet the RPS requirement within each state. For example, New Jersey needs approximately 368 MW online for the entire 2012 reporting year to meet the RPS requirement. Additionally, the data presented above does not include projects that are in the pipeline or currently going through the registration process in each state program. This data represents specifically the projects that have been approved for the corresponding state SREC markets as of the dates noted.

Solar Capacity in the SREC States – June 2011

Posted July 5th, 2011 by SRECTrade.

SRECTrade SREC Markets Report: June 2011

The following post outlines the megawatts of solar capacity certified and/or registered to create SRECs in the SREC markets SRECTrade currently serves.

For a PDF copy of this table click here.

Capacity_June2011_1

PJM Eligible Systems

As of the end of June, there were 16,381 solar PV (16,069) and solar thermal (312) systems registered and eligible to create SRECs in the PJM Generation Attribute Tracking System (GATS) registry. Of these eligible systems, 65 (0.40%) have a nameplate capacity of 1 megawatt or greater, of which only 4 systems are greater than 5 MW. The largest system, currently located in New Jersey, is 18.3 MW,  and the second largest, located in Ohio is 12 MW. The third largest system, at 10 MW, is located in IL and eligible for the MD, PA, and DC SREC markets. The fourth largest, at 6.2 MW, is located in New Jersey.

New Energy Year To Begin for DE, NJ, and PA

June 1, 2011 marks the beginning of the new energy year for DE, NJ, and PA. All requirements for these markets increase given their RPS solar carve out schedules. SRECs for the month of June, the first creation period for the new reporting year, will be minted at the end of July.

Delaware: The reporting year 2011-2012 requirement for DE equates to approximately 21 MW being online for the entire year or approximately 25,600 SRECs created. As of June 30, 2011, 9.1 MW of solar capacity was registered and eligible to create DE SRECs in PJM GATS.

New Jersey: The reporting year 2012 requirement for NJ equates to approximately 368 MW being online for the entire year with a fixed SREC requirement of 442,000 MWhs. As of June 30, 2011, 332 MW of solar capacity was registered and eligible to create NJ SRECs in PJM GATS. As of April 30, 2011, the NJ Office of Clean Energy (NJOCE) reported that 330.5 MW (9,181 projects) of solar had been installed in the state. The NJOCE data shows that from November 2010 – April 2011, the average installed capacity per month was 18 MW. Forecasts prepared by the NJOCE, show the monthly rate of installation through September 2011 ranging between 17 – 30 MW per month depending on different scenarios.

Pennsylvania: The reporting year 2012 requirement for PA equates to approximately 44 MW being online for the entire year or approximately 53,000 SRECs created. As of June 30, 2011, 104.8 MW of solar capacity was registered and eligible to create PA SRECs in PJM GATS.

Massachusetts DOER Qualified Projects

As of May 6, 2011, there were 524 MA DOER qualified solar projects; 467 operational and 57 not operational. Of these qualified systems, 11 (2.1%) have a nameplate capacity of 1 megawatt or greater, of which only 3 are between 1.5 and 2 MW. Three of the projects greater than 1 MW are currently operational.

Capacity Summary By State

The tables above demonstrate the capacity breakout by state. Note, that for all PJM GATS registered projects, each state includes all projects certified to sell into that state. State RPS programs that allow for systems sited in other states to participate have been broken up by systems sited in state and out of state. Additional detail has been provided to demonstrate the total capacity of systems only certified for one specific state market versus being certified for multiple state markets. For example, PA includes projects only certified to sell into the PA SREC market, broken out by in state and out of state systems, as well as projects that are also certified to sell into PA and Other State markets broken out by in state and out of state systems (i.e. OH, DC, MD, DE, NJ). PA Out of State includes systems sited in states with their own state SREC market (i.e. DE) as well as systems sited in states that have no SREC market (i.e. VA). Also, it is important to note that the Current Capacity represents the total megawatts eligible to produce and sell SRECs as of the noted date, while the Estimated Required Capacity – Current and Next Reporting Year represents the estimated number of MW that need to be online on average throughout the reporting period to meet the RPS requirement within each state. For example, New Jersey needs approximately 255 MW online for the entire 2011 reporting year to meet the RPS requirement. Additionally, the data presented above does not include projects that are in the pipeline or currently going through the registration process in each state program. This data represents specifically the projects that have been approved for the corresponding state SREC markets as of the dates noted.

Solar Capacity in the SREC States – May 2011

Posted June 1st, 2011 by SRECTrade.

SRECTrade SREC Markets Report: May 2011

The following post outlines the megawatts of solar capacity certified and/or registered to create SRECs in the SREC markets SRECTrade currently serves.

May 2011 Updated JPEG

PJM Eligible Systems

As of the end of May, there were 15,480 solar PV (15,203) and solar thermal (277) systems registered and eligible to create SRECs in the PJM Generation Attribute Tracking System (GATS) registry. Of these eligible systems, 59 (0.38%) have a nameplate capacity of 1 megawatt or greater, of which only 3 systems are greater than 5 MW. The largest system, currently located in New Jersey, is 18.3 MW,  and the second largest, located in Ohio is 12 MW. The third largest system, is located in IL and eligible for the MD, PA, and DC SREC markets, is 10 MW.

Massachusetts DOER Qualified Projects

As of May 6, 2011, there were 524 MA DOER qualified solar projects; 467 operational and 57 not operational. Of these qualified systems, 11 (2.1%) have a nameplate capacity of 1 megawatt or greater, of which only 3 are between 1.5 and 2 MW. Three of the projects greater than 1 MW are currently operational.

Capacity Summary By State

The tables above demonstrate the capacity breakout by state. Note, that for all PJM GATS registered projects, each state includes all projects certified to sell into that state. State RPS programs that allow for systems sited in other states to participate have been broken up by systems sited in state and out of state. Additional detail has been provided to demonstrate the total capacity of systems only certified for one specific state market versus being certified for multiple state markets. For example, PA includes projects only certified to sell into the PA SREC market, broken out by in state and out of state systems, as well as projects that are also certified to sell into PA and Other State markets broken out by in state and out of state systems (i.e. OH, DC, MD, DE, NJ). PA Out of State includes systems sited in states with their own state SREC market (i.e. DE) as well as systems sited in states that have no SREC market (i.e. VA). Also, it is important to note that the Current Capacity represents the total megawatts eligible to produce and sell SRECs as of the noted date, while the Estimated Required Capacity – Current and Next Reporting Year represents the estimated number of MW that need to be online on average throughout the reporting period to meet the RPS requirement within each state. For example, New Jersey needs approximately 255 MW online for the entire 2011 reporting year to meet the RPS requirement. Additionally, the data presented above does not include projects that are in the pipeline or currently going through the registration process in each state program. This data represents specifically the projects that have been approved for the corresponding state SREC markets as of the dates noted.

Subscribe

Solar Capacity in the SREC States – April 2011

Posted May 4th, 2011 by SRECTrade.

SRECTrade SREC Markets Report: April 2011

The following post outlines the megawatts of solar capacity certified and/or registered to create SRECs in the SREC markets SRECTrade currently serves.

GATS_MA_Generators_April_2011_v1

PJM Eligible Systems

As of the end of April, there were 14,598 solar PV (14,344) and solar thermal (254) systems registered and eligible to create SRECs in the PJM Generation Attribute Tracking System (GATS) registry. Of these eligible systems, 52 (0.36%) have a nameplate capacity of 1 megawatt or greater, of which only 3 systems are greater than 5 MW. The largest system, currently located in Ohio, is 12 MW,  and the second largest, located in Chicago and eligible for the PA, DC, and MD markets, is 10 MW. The third largest system, located in NJ, is 5.6 MW.

Massachusetts DOER Qualified Projects

As of April 13, 2011, there were 524 MA DOER qualified solar projects; 467 operational and 57 not operational. Of these qualified systems, 11 (2.1%) have a nameplate capacity of 1 megawatt or greater, of which only 3 are between 1.5 and 2 MW. Three of the projects greater than 1 MW are currently operational.

Capacity Summary By State

The tables above demonstrate the capacity breakout by state. Note, that for all PJM GATS registered projects, each state includes all projects certified to sell into that state. State RPS programs that allow for systems sited in other states to participate have been broken up by systems sited in state and out of state. Additional detail has been provided to demonstrate the total capacity of systems only certified for one specific state market versus being certified for multiple state markets. For example, PA includes projects only certified to sell into the PA SREC market, broken out by in state and out of state systems, as well as projects that are also certified to sell into PA and Other State markets broken out by in state and out of state systems (i.e. OH, DC, MD, DE, NJ). PA Out of State includes systems sited in states with their own state SREC market (i.e. DE) as well as systems sited in states that have no SREC market (i.e. VA). Also, it is important to note that the Current Capacity represents the total megawatts eligible to produce and sell SRECs as of the noted date, while the Estimated Required Capacity – Current and Next Reporting Year represents the estimated number of MW that need to be online on average throughout the reporting period to meet the RPS requirement within each state. For example, New Jersey needs approximately 255 MW online for the entire 2011 reporting year to meet the RPS requirement. Additionally, the data presented above does not include projects that are in the pipeline or currently going through the registration process in each state program. This data represents specifically the projects that have been approved for the corresponding state SREC markets as of the dates noted.

Subscribe


First Massachusetts SRECs created!

Posted July 21st, 2010 by SRECTrade.

The first set of SRECs eligible for the Massachusetts solar carve-out were created in the SRECTrade aggregation on July 15, 2010. These SRECs represent Q1 2010 generation and over 50% of the total share of SRECs created in NEPOOL GIS for Q1 2010 can be attributed to customers of SRECTrade.  With partners like SunBug Solar, Alteris Renewables, Sunlight Solar, My Generation Energy and more, the SRECTrade marketplace is quickly becoming the platform of  choice for installers searching for an efficient, transparent and cost-effective way to serve the SREC needs of their clients.

One key benefit of SRECTrade’s aggregation is that the customer owns and controls their SRECs until sold to a buyer in the auctions or the forwards market.  Each SREC created in the SRECTrade aggregation is attributed to a single facility. Other aggregations may require a contract that does not allow for flexibility because the generation from multiple facilities is lumped together to create a single SREC.  You don’t have your own SRECs, but your electricity gets counted toward a portion of the aggregate’s SRECs.  With SRECTrade’s aggregation, you own your SRECs until you tell us what to do with them. Our goal is to provide the most effective platform in Massachusetts along with the best customer service in the business.

Now that Q1 2010 SRECs are created, SRECTrade will close the first MA SREC auction on August 6, 2010. Auctions will be available monthly, but since SRECs are generated quarterly, the first auction after quarter-end will always have the most volume.  Q2 2010 SRECs will be available on October 15, 2010 and available starting with the November auction.