Posts Tagged ‘Renewable Energy Certificates’

Delaware PSC Approves SREC Procurement Pilot Program

Posted November 15th, 2011 by SRECTrade.

The Delaware Public Service Commission approved the SREC Procurement Pilot Program on November 8th, 2011. This program will allow qualified solar energy system owners to sell their SRECs at a fixed price for the next 20 years.

The program will only be open to certain DE solar owners, for example, eligible facility owners must have received approval of their “Accepted Completed Solar System Interconnection Application” on or after December 1st 2010. Another requirement stipulates that the facility must not have received supplemental funding from a public source other than grants associated with the Delaware Green Energy Program “GEP”.

The number of SRECs to be procured is tiered according to the system size from which they are obtained. They will also be priced accordingly. Based on the requirements for June 2011 through May 2012, the numbers and price are

Tier Size (kW) Number of SRECs Percentage of Total SRECs Price, 1st 10 years Price, next 10 years
1 <50 2972 13.4% $260 base, $235 alt+ $50
2a 50 – 250 2,000 9.1% $240 base, $175 alt+ $50
2b 250 – 500 2,000 9.1% Lowest Bid Price* $50
3 500 – 2,000 4,500 20.4% Lowest Bid Price* $50
4 >2,000 10,600 48% Lowest Bid Price* $50
+Alternative pricing for projects that received a GEP grant before December 10 2010.
* Prices for tiers 2b, 3 and 4 will be decided by competitive bidding amongst the applicants.

In the event of oversubscription for facilities in Tier 1 and 2A, systems will be eliminated via lottery, starting with systems enrolled in the equipment or workforce bonus program.

Payments will be made quarterly for Tier 1 and monthly for Tiers 2 and 3. The energy production must be measured by at least a standard, utility grade meter and online monitoring for Tier 1 systems, and a revenue grade meter with online monitoring for Tiers 2 and 3.

Facilities are obliged to deliver the number of SRECs as estimated for their system size when they apply. The Sustainable Energy Utility is obliged to purchase up to 110% of the estimated SRECs, but may choose not to purchase any additional surplus SRECs.

This program will likely commence this winter or spring, and SRECTrade will be supporting this program for all of our installers and their customers. Look out for a future email regarding the SREC Pilot Program.

Solar Capacity in the SREC States – August 2011

Posted August 26th, 2011 by SRECTrade.

SRECTrade SREC Markets Report: August 2011

The following post outlines the megawatts of solar capacity certified and/or registered to create SRECs in the SREC markets SRECTrade currently serves.

For a PDF copy of this table click here.

Renewable Generators in GATS 8_25_11_v4

PJM Eligible Systems

As of the end of August, there were 18,112 solar PV (17,791) and solar thermal (321) systems registered and eligible to create SRECs in the PJM Generation Attribute Tracking System (GATS) registry. Of these eligible systems, 77 (0.43%) have a nameplate capacity of 1 megawatt or greater, of which only 6 systems are greater than 5 MW. The largest system, currently located in New Jersey, is 18.3 MW, and the second largest, located in Ohio is 12 MW. The third largest system, at 11.2 MW, is located in Delaware.

Beginning of energy year for DE, NJ, and PA

June 1, 2011 marked the beginning of the new energy year for DE, NJ, and PA. All requirements for these markets increase given their RPS solar carve out schedules. SRECs for the month of July, the second creation period for the new reporting year, will be minted at the end of August.

Delaware: The reporting year 2011-2012 requirement for DE equates to approximately 21 MW being online for the entire year or approximately 25,600 SRECs created. As of August 25, 2011, 20.5 MW of solar capacity was registered and eligible to create DE SRECs in PJM GATS. 11.2 MW of the 20.5 MW currently eligible is from the Dover Sun Park project developed by LS Power. In the 2011-12 compliance year, Delmarva Power has contracted to purchase 9,846 SRECs from the project, of which 7,000 are being held by the Sustainable Energy Utility (SEU) until 2015-16*.

New Jersey: The reporting year 2012 requirement for NJ equates to approximately 368 MW being online for the entire year with a fixed SREC requirement of 442,000 MWhs. As of August 25, 2011, 379 MW of solar capacity was registered and eligible to create NJ SRECs in PJM GATS. While this figure represents all projects registered in GATS, there are recently installed projects awaiting issuance of a New Jersey state certification number. This delay results in a portion of installed projects not yet represented in the 379 MW figure. On July 26, 2011 the NJ Office of Clean Energy (NJ OCE) reported that as of June 30, 2011 more than 380 MW (10,086 projects) of solar had been installed in NJ. The news release noted that 40 MW were installed in the month of June. The installation data for July 2011 has not yet been released by the NJ OCE. For more details on the the current NJ market conditions see this post.

Pennsylvania: The reporting year 2012 requirement for PA equates to approximately 44 MW being online for the entire year or approximately 53,000 SRECs created. As of August 25, 2011, 124.5 MW of solar capacity was registered and eligible to create PA SRECs in PJM GATS.

Massachusetts DOER Qualified Projects

As of August 15, 2011, there were 861 MA DOER qualified solar projects; 829 operational and 32 not operational. Of these qualified systems, 11 (1.3%) have a nameplate capacity of 1 megawatt or greater, of which only 3 are between 1.5 and 2 MW. Three of the projects greater than 1 MW are currently operational.

Capacity Summary By State

The tables above demonstrate the capacity breakout by state. Note, that for all PJM GATS registered projects, each state includes all projects certified to sell into that state. State RPS programs that allow for systems sited in other states to participate have been broken up by systems sited in state and out of state. Additional detail has been provided to demonstrate the total capacity of systems only certified for one specific state market versus being certified for multiple state markets. For example, PA includes projects only certified to sell into the PA SREC market, broken out by in state and out of state systems, as well as projects that are also certified to sell into PA and Other State markets broken out by in state and out of state systems (i.e. OH, DC, MD, DE, NJ). PA Out of State includes systems sited in states with their own state SREC market (i.e. DE) as well as systems sited in states that have no SREC market (i.e. VA). Also, it is important to note that the Current Capacity represents the total megawatts eligible to produce and sell SRECs as of the noted date, while the Estimated Required Capacity – Current and Next Reporting Year represents the estimated number of MW that need to be online on average throughout the reporting period to meet the RPS requirement within each state. For example, New Jersey needs approximately 368 MW online for the entire 2012 reporting year to meet the RPS requirement. Additionally, the data presented above does not include projects that are in the pipeline or currently going through the registration process in each state program. This data represents specifically the projects that have been approved for the corresponding state SREC markets as of the dates noted.

*Source: State of Delaware Pilot Program For the Procurement of Solar Renewable Energy Credits: Recommendations of the Renewable Energy Taskforce

Solar Capacity in the SREC States – July 2011

Posted July 26th, 2011 by SRECTrade.

SRECTrade SREC Markets Report: July 2011

The following post outlines the megawatts of solar capacity certified and/or registered to create SRECs in the SREC markets SRECTrade currently serves.

For a PDF copy of this table click here.

Capacity_July11

PJM Eligible Systems

As of the end of July, there were 17,106 solar PV (16,792) and solar thermal (314) systems registered and eligible to create SRECs in the PJM Generation Attribute Tracking System (GATS) registry. Of these eligible systems, 70 (0.40%) have a nameplate capacity of 1 megawatt or greater, of which only 4 systems are greater than 5 MW. The largest system, currently located in New Jersey, is 18.3 MW, and the second largest, located in Ohio is 12 MW. The third largest system, at 10 MW, is located in IL and eligible for the MD, PA, and DC SREC markets. The fourth largest, at 6.2 MW, is located in New Jersey.

New Energy Year To Begin for DE, NJ, and PA

June 1, 2011 marks the beginning of the new energy year for DE, NJ, and PA. All requirements for these markets increase given their RPS solar carve out schedules. SRECs for the month of June, the first creation period for the new reporting year, will be minted at the end of July.

Delaware: The reporting year 2011-2012 requirement for DE equates to approximately 21 MW being online for the entire year or approximately 25,600 SRECs created. As of July 25, 2011, 9.1 MW of solar capacity was registered and eligible to create DE SRECs in PJM GATS.

New Jersey: The reporting year 2012 requirement for NJ equates to approximately 368 MW being online for the entire year with a fixed SREC requirement of 442,000 MWhs. As of July 25, 2011, 347.5 MW of solar capacity was registered and eligible to create NJ SRECs in PJM GATS. While this figure represents all projects registered in GATS, there are recently installed projects awaiting issuance of a New Jersey state certification number. This delay results in a portion of installed projects not yet represented in the 347.5 MW figure. On July 26, 2011 the NJ Office of Clean Energy (NJ OCE) reported that as of June 30, 2011 more than 380 MW (10,086 projects) of solar had been installed in NJ. The news release noted that 40 MW were installed in the month of June.

Pennsylvania: The reporting year 2012 requirement for PA equates to approximately 44 MW being online for the entire year or approximately 53,000 SRECs created. As of July 25, 2011, 115.7 MW of solar capacity was registered and eligible to create PA SRECs in PJM GATS.

Massachusetts DOER Qualified Projects

As of July 11, 2011, there were 682 MA DOER qualified solar projects; 649 operational and 33 not operational. Of these qualified systems, 11 (1.6%) have a nameplate capacity of 1 megawatt or greater, of which only 3 are between 1.5 and 2 MW. Three of the projects greater than 1 MW are currently operational.

Capacity Summary By State

The tables above demonstrate the capacity breakout by state. Note, that for all PJM GATS registered projects, each state includes all projects certified to sell into that state. State RPS programs that allow for systems sited in other states to participate have been broken up by systems sited in state and out of state. Additional detail has been provided to demonstrate the total capacity of systems only certified for one specific state market versus being certified for multiple state markets. For example, PA includes projects only certified to sell into the PA SREC market, broken out by in state and out of state systems, as well as projects that are also certified to sell into PA and Other State markets broken out by in state and out of state systems (i.e. OH, DC, MD, DE, NJ). PA Out of State includes systems sited in states with their own state SREC market (i.e. DE) as well as systems sited in states that have no SREC market (i.e. VA). Also, it is important to note that the Current Capacity represents the total megawatts eligible to produce and sell SRECs as of the noted date, while the Estimated Required Capacity – Current and Next Reporting Year represents the estimated number of MW that need to be online on average throughout the reporting period to meet the RPS requirement within each state. For example, New Jersey needs approximately 368 MW online for the entire 2012 reporting year to meet the RPS requirement. Additionally, the data presented above does not include projects that are in the pipeline or currently going through the registration process in each state program. This data represents specifically the projects that have been approved for the corresponding state SREC markets as of the dates noted.

Solar Capacity in the SREC States – June 2011

Posted July 5th, 2011 by SRECTrade.

SRECTrade SREC Markets Report: June 2011

The following post outlines the megawatts of solar capacity certified and/or registered to create SRECs in the SREC markets SRECTrade currently serves.

For a PDF copy of this table click here.

Capacity_June2011_1

PJM Eligible Systems

As of the end of June, there were 16,381 solar PV (16,069) and solar thermal (312) systems registered and eligible to create SRECs in the PJM Generation Attribute Tracking System (GATS) registry. Of these eligible systems, 65 (0.40%) have a nameplate capacity of 1 megawatt or greater, of which only 4 systems are greater than 5 MW. The largest system, currently located in New Jersey, is 18.3 MW,  and the second largest, located in Ohio is 12 MW. The third largest system, at 10 MW, is located in IL and eligible for the MD, PA, and DC SREC markets. The fourth largest, at 6.2 MW, is located in New Jersey.

New Energy Year To Begin for DE, NJ, and PA

June 1, 2011 marks the beginning of the new energy year for DE, NJ, and PA. All requirements for these markets increase given their RPS solar carve out schedules. SRECs for the month of June, the first creation period for the new reporting year, will be minted at the end of July.

Delaware: The reporting year 2011-2012 requirement for DE equates to approximately 21 MW being online for the entire year or approximately 25,600 SRECs created. As of June 30, 2011, 9.1 MW of solar capacity was registered and eligible to create DE SRECs in PJM GATS.

New Jersey: The reporting year 2012 requirement for NJ equates to approximately 368 MW being online for the entire year with a fixed SREC requirement of 442,000 MWhs. As of June 30, 2011, 332 MW of solar capacity was registered and eligible to create NJ SRECs in PJM GATS. As of April 30, 2011, the NJ Office of Clean Energy (NJOCE) reported that 330.5 MW (9,181 projects) of solar had been installed in the state. The NJOCE data shows that from November 2010 – April 2011, the average installed capacity per month was 18 MW. Forecasts prepared by the NJOCE, show the monthly rate of installation through September 2011 ranging between 17 – 30 MW per month depending on different scenarios.

Pennsylvania: The reporting year 2012 requirement for PA equates to approximately 44 MW being online for the entire year or approximately 53,000 SRECs created. As of June 30, 2011, 104.8 MW of solar capacity was registered and eligible to create PA SRECs in PJM GATS.

Massachusetts DOER Qualified Projects

As of May 6, 2011, there were 524 MA DOER qualified solar projects; 467 operational and 57 not operational. Of these qualified systems, 11 (2.1%) have a nameplate capacity of 1 megawatt or greater, of which only 3 are between 1.5 and 2 MW. Three of the projects greater than 1 MW are currently operational.

Capacity Summary By State

The tables above demonstrate the capacity breakout by state. Note, that for all PJM GATS registered projects, each state includes all projects certified to sell into that state. State RPS programs that allow for systems sited in other states to participate have been broken up by systems sited in state and out of state. Additional detail has been provided to demonstrate the total capacity of systems only certified for one specific state market versus being certified for multiple state markets. For example, PA includes projects only certified to sell into the PA SREC market, broken out by in state and out of state systems, as well as projects that are also certified to sell into PA and Other State markets broken out by in state and out of state systems (i.e. OH, DC, MD, DE, NJ). PA Out of State includes systems sited in states with their own state SREC market (i.e. DE) as well as systems sited in states that have no SREC market (i.e. VA). Also, it is important to note that the Current Capacity represents the total megawatts eligible to produce and sell SRECs as of the noted date, while the Estimated Required Capacity – Current and Next Reporting Year represents the estimated number of MW that need to be online on average throughout the reporting period to meet the RPS requirement within each state. For example, New Jersey needs approximately 255 MW online for the entire 2011 reporting year to meet the RPS requirement. Additionally, the data presented above does not include projects that are in the pipeline or currently going through the registration process in each state program. This data represents specifically the projects that have been approved for the corresponding state SREC markets as of the dates noted.

Solar Capacity in the SREC States – May 2011

Posted June 1st, 2011 by SRECTrade.

SRECTrade SREC Markets Report: May 2011

The following post outlines the megawatts of solar capacity certified and/or registered to create SRECs in the SREC markets SRECTrade currently serves.

May 2011 Updated JPEG

PJM Eligible Systems

As of the end of May, there were 15,480 solar PV (15,203) and solar thermal (277) systems registered and eligible to create SRECs in the PJM Generation Attribute Tracking System (GATS) registry. Of these eligible systems, 59 (0.38%) have a nameplate capacity of 1 megawatt or greater, of which only 3 systems are greater than 5 MW. The largest system, currently located in New Jersey, is 18.3 MW,  and the second largest, located in Ohio is 12 MW. The third largest system, is located in IL and eligible for the MD, PA, and DC SREC markets, is 10 MW.

Massachusetts DOER Qualified Projects

As of May 6, 2011, there were 524 MA DOER qualified solar projects; 467 operational and 57 not operational. Of these qualified systems, 11 (2.1%) have a nameplate capacity of 1 megawatt or greater, of which only 3 are between 1.5 and 2 MW. Three of the projects greater than 1 MW are currently operational.

Capacity Summary By State

The tables above demonstrate the capacity breakout by state. Note, that for all PJM GATS registered projects, each state includes all projects certified to sell into that state. State RPS programs that allow for systems sited in other states to participate have been broken up by systems sited in state and out of state. Additional detail has been provided to demonstrate the total capacity of systems only certified for one specific state market versus being certified for multiple state markets. For example, PA includes projects only certified to sell into the PA SREC market, broken out by in state and out of state systems, as well as projects that are also certified to sell into PA and Other State markets broken out by in state and out of state systems (i.e. OH, DC, MD, DE, NJ). PA Out of State includes systems sited in states with their own state SREC market (i.e. DE) as well as systems sited in states that have no SREC market (i.e. VA). Also, it is important to note that the Current Capacity represents the total megawatts eligible to produce and sell SRECs as of the noted date, while the Estimated Required Capacity – Current and Next Reporting Year represents the estimated number of MW that need to be online on average throughout the reporting period to meet the RPS requirement within each state. For example, New Jersey needs approximately 255 MW online for the entire 2011 reporting year to meet the RPS requirement. Additionally, the data presented above does not include projects that are in the pipeline or currently going through the registration process in each state program. This data represents specifically the projects that have been approved for the corresponding state SREC markets as of the dates noted.

Subscribe

Solar Capacity in the SREC States – April 2011

Posted May 4th, 2011 by SRECTrade.

SRECTrade SREC Markets Report: April 2011

The following post outlines the megawatts of solar capacity certified and/or registered to create SRECs in the SREC markets SRECTrade currently serves.

GATS_MA_Generators_April_2011_v1

PJM Eligible Systems

As of the end of April, there were 14,598 solar PV (14,344) and solar thermal (254) systems registered and eligible to create SRECs in the PJM Generation Attribute Tracking System (GATS) registry. Of these eligible systems, 52 (0.36%) have a nameplate capacity of 1 megawatt or greater, of which only 3 systems are greater than 5 MW. The largest system, currently located in Ohio, is 12 MW,  and the second largest, located in Chicago and eligible for the PA, DC, and MD markets, is 10 MW. The third largest system, located in NJ, is 5.6 MW.

Massachusetts DOER Qualified Projects

As of April 13, 2011, there were 524 MA DOER qualified solar projects; 467 operational and 57 not operational. Of these qualified systems, 11 (2.1%) have a nameplate capacity of 1 megawatt or greater, of which only 3 are between 1.5 and 2 MW. Three of the projects greater than 1 MW are currently operational.

Capacity Summary By State

The tables above demonstrate the capacity breakout by state. Note, that for all PJM GATS registered projects, each state includes all projects certified to sell into that state. State RPS programs that allow for systems sited in other states to participate have been broken up by systems sited in state and out of state. Additional detail has been provided to demonstrate the total capacity of systems only certified for one specific state market versus being certified for multiple state markets. For example, PA includes projects only certified to sell into the PA SREC market, broken out by in state and out of state systems, as well as projects that are also certified to sell into PA and Other State markets broken out by in state and out of state systems (i.e. OH, DC, MD, DE, NJ). PA Out of State includes systems sited in states with their own state SREC market (i.e. DE) as well as systems sited in states that have no SREC market (i.e. VA). Also, it is important to note that the Current Capacity represents the total megawatts eligible to produce and sell SRECs as of the noted date, while the Estimated Required Capacity – Current and Next Reporting Year represents the estimated number of MW that need to be online on average throughout the reporting period to meet the RPS requirement within each state. For example, New Jersey needs approximately 255 MW online for the entire 2011 reporting year to meet the RPS requirement. Additionally, the data presented above does not include projects that are in the pipeline or currently going through the registration process in each state program. This data represents specifically the projects that have been approved for the corresponding state SREC markets as of the dates noted.

Subscribe


Solar Capacity in the SREC States – March 2011

Posted April 4th, 2011 by SRECTrade.

SRECTrade SREC Markets Report: March 2011

The following post outlines the megawatts of solar capacity certified and/or registered to create SRECs in the SREC markets SRECTrade currently serves.

Summary JPEG

PJM Eligible Systems

As of the end of March, there were 13,888 solar PV (13,634) and solar thermal (254) systems registered and eligible to create SRECs in the PJM Generation Attribute Tracking System (GATS) registry. Of these eligible systems, 46 (0.33%) have a nameplate capacity of 1 megawatt or greater, of which only 3 systems are greater than 5 MW. The largest system, currently located in Ohio, is 12 MW,  and the second largest, located in Chicago and eligible for the PA, DC, and MD markets, is 10 MW. The third largest system, located in NJ, is 5.6 MW.

Massachusetts DOER Qualified Projects

As of March 16, 2011, there were 337 MA DOER qualified solar projects; 314 operational and 23 not operational. Of these qualified systems, 11 (3.3%) have a nameplate capacity of 1 megawatt or greater, of which only 3 are between 1.5 and 2 MW. Two of the projects greater than 1 MW are currently operational.

Capacity Summary By State

The tables above demonstrate the capacity breakout by state. Note, that for all PJM GATS registered projects, each state includes all projects certified to sell into that state. State RPS programs that allow for systems sited in other states to participate have been broken up by systems sited in state and out of state. Additional detail has been provided to demonstrate the total capacity of systems only certified for one specific state market versus being certified for multiple state markets. For example, PA includes projects only certified to sell into the PA SREC market, broken out by in state and out of state systems, as well as projects that are also certified to sell into PA and Other State markets broken out by in state and out of state systems (i.e. OH, DC, MD, DE, NJ). PA Out of State includes systems sited in states with their own state SREC market (i.e. DE) as well as systems sited in states that have no SREC market (i.e. VA). Also, it is important to note that the Current Capacity represents the total megawatts eligible to produce and sell SRECs as of the noted date, while the Estimated Required Capacity – Current and Next Reporting Year represents the estimated number of MW that need to be online on average throughout the reporting period to meet the RPS requirement within each state. For example, New Jersey needs approximately 255 MW online for the entire 2011 reporting year to meet the RPS requirement. Additionally, the data presented above does not include projects that are in the pipeline or currently going through the registration process in each state program. This data represents specifically the projects that have been approved for the corresponding state SREC markets as of the dates noted.

Subscribe


Solar Capacity in the SREC States – December 2010

Posted January 5th, 2011 by SRECTrade.

SRECTrade SREC Markets Report: December 2010

The following post outlines the megawatts of solar capacity certified and/or registered to create SRECs in the SREC markets SRECTrade currently serves.

PJM Eligible Systems

As of the end of December, there were 11,241 solar PV (11,015) and solar thermal (226) systems registered and eligible to create SRECs in the PJM Generation Attribute Tracking System registry. Of these eligible systems, 35 (~0.3%) have a nameplate capacity of 1 megawatt or greater, of which only 3 systems are greater than 5 MW. The largest system, currently located in Ohio, is 12 MW,  and the second largest, located in Chicago and eligible for the PA and DC markets, is 10 MW. The third largest system, located in NJ, is 5.6 MW.

Massachusetts DOER Qualified Projects

As of December 10, 2010, there were 180 MA DOER qualified solar projects; 156 operational and 24 not operational. Of these qualified systems, 9 (~5.0%) have a nameplate capacity of 1 megawatt or greater, of which only 2 are between 1.5 and 2 MW. None of the projects greater than 1 MW are currently operational.

Capacity Summary By State

The tables below demonstrate the capacity breakout by state. Note, that for all PJM GATS registered projects, each state includes all projects certified to sell into that state. State RPS programs that allow for systems sited in other states to participate have been broken up by systems sited in state and out of state. For example, PA In State includes projects eligible to sell into the PA SREC market as well as projects that may also be eligible to sell into OH and DC. PA Out of State includes systems sited in states with their own state SREC market (i.e. DE) as well as systems sited in states that have no SREC market (i.e. VA). Also, it is important to note that the Current Capacity represents the total megawatts eligible to produce and sell SRECs as of the noted date, while the Estimated Required Capacity – Current and Next Reporting Year represents the estimated number of MW that need to be online on average throughout the reporting period to meet the RPS requirement within each state. For example, New Jersey needs approximately 255 MW online for the entire 2011 reporting year to meet the RPS requirement. Additionally, the data presented below does not include projects that are in the pipeline or currently going through the registration process in each state program. This data represents specifically the projects that have been approved for the corresponding state SREC markets to date.

Dec JPEG Image updated

Subscribe

Senators Introduce Renewable Electricity Standard

Posted October 20th, 2010 by SRECTrade.

At the end of September, Senators Jeff Bingaman, Sam Brownback, Byron Dorgan, Susan Collins, Tom Udall, and Mark Udall introduced a Renewable Electricity Standard (RES). The bill will require electricity generators to acquire specific percentages of electricity supplied to customers from renewable energy sources.

Senator Bingaman commented, “I think that the votes are present in the Senate to pass a renewable electricity standard.  I think that they are present in the House.  I think that we need to get on with figuring out what we can pass and move forward.”

The legislation proposes the following targets to be met from either renewable energy resources or energy efficiency improvements:

YEAR  __                 %

2012-2013…….……..3

2014-2016…….……. 6

2017-2018…….……. 9

2019-2020………… 12

2021-2039………… 15

Eligible renewable energy resources will include wind, solar, ocean, geothermal, biomass, landfill gas, incremental hydropower, hydrokinetic, new hydropower at existing dams and waste-to-energy. Energy providers can comply with the RES by producing renewable energy, implementing energy efficiency measures, purchasing renewable energy or energy efficiency savings, purchasing renewable energy credits or energy efficiency credits, or paying an alternative compliance payment (ACP) at a rate of $21/MWh. The national RES program will not affect state programs.

Click here for the entire press release.