Solar Capacity in the SREC States – May 2012

Posted June 11th, 2012 by SRECTrade.

SRECTrade SREC Markets Report: May 2012

The following post outlines the megawatts of solar capacity certified and/or registered to create SRECs in the Solar REC markets SRECTrade currently serves.

A PDF copy of this table can be found here.

PJM Eligible Systems

As of this writing, there were 25,753 solar PV and 340 solar thermal systems registered and eligible to create SRECs in the PJM Generation Attribute Tracking System (GATS). Of these eligible systems, 161 (0.62%) have a nameplate capacity of 1 megawatt or greater, of which 16 systems are greater than 5 MW. The largest system, the PSE&G utility pole mount project located in New Jersey, is 25.1 MW, and the second largest, located in New Jersey is 12.5 MW. The third largest system, at 12 MW, is located in Ohio.

Delaware: The reporting year 2011-12 (6/1/11 – 5/31/12) requirement for DE equates to approximately 23,700 SRECs being retired. If all retired SRECs were of DE2011-12 vintage, approximately 19.8 MW would need to be operational all year long. As of June 11, 2012, 28.2 MW of solar capacity was registered and eligible to create DE SRECs in PJM GATS. 11.2 MW of the 28.2 MW currently eligible is from the Dover Sun Park project developed by LS Power. In the 2011-12 compliance year, Delmarva Power has contracted to purchase 9,846 SRECs from the project, of which 7,000 are being held by the Sustainable Energy Utility (SEU) until 2015-16*. Additionally, the DE SREC Pilot Program solicitation recently closed its first solicitation. As of June11, 2012, PJM GATS reported the issuance of approximately 27,300 DE2011-12 vintage SRECs. Additional SRECs from prior eligible periods may also impact the market should there be a demand for these older vintage SRECs.

Maryland: The end of February marked the first issuance period of MD2012 SRECs in PJM GATS. As of June 11, 2012, 50.3 MW of MD sited solar capacity was registered to create MD eligible SRECs. 2012 Solar RPS requirements are estimated at 56.1 MW or approximately 67,310 SRECs. MD Governor, Martin O’Malley recently signed into law legislation to pull forward the RPS requirements. As of June 11, 2012, PJM GATS reported the issuance of approximately 15,800 MD2012 SRECs. Additionally, all out-of-state MD systems are no longer eligible to produce MD certified SRECs and their MD certification numbers have been removed from their systems in PJM GATS. Lastly, there are MD sited SRECs available from prior eligible periods, which could be utilized for compliance needs in 2012.

New Jersey: The New Jersey 2012 reporting year requires 442,000 SRECs to be retired. This equates to approximately 368 MW of capacity being operational all year long, assuming all requirements were met with current vintage year SRECs. As of June 11, 2012, 756.5 MW of solar capacity was registered and eligible to create NJ SRECs in PJM GATS. While this figure represents all projects registered in GATS, there are recently installed projects awaiting issuance of a New Jersey state certification number. This delay results in a portion of installed projects not yet represented in the 756.5 MW figure. As of April 30, 2012 the NJ Office of Clean Energy (NJ OCE) reported that 770.0 MW of solar had been installed in NJ. Additionally, estimates through May 2012 show 802.3 MW of total installed capacity. For more information on the status of the NJ market and information on the expected legislation to adjust the Solar RPS see the following: New Jersey Legislation Update: A2966. As of June 11, 2012, PJM GATS reported the issuance of approximately 558,400 NJ2012 SRECs. This figure surpasses the current 2012 compliance year requirement of 442,000 SRECs by approximately 116,000 SRECs. Given current installed capacity, we estimate the market will be oversupplied by more than 200,000 NJ2012 SRECs.

Ohio: Ohio’s 2012 RPS solar target requires approximately 95,300 SRECs to be retired by the end of the compliance period. At least 50% of the SREC requirement must come from systems sited in the state. As of June 11, 2012, 49.0 MW of in-state capacity and 89.3 MW of out-of-state capacity were eligible to generate OH SRECs. A large increase of in-state capacity recently came from a 9.8 MW project sited at the Campbell Soup facility in Napoleon, OH. As of June 11, 2012, GATS issued approximately 16,400 in-state and 33,000 out-of-state OH2012 eligible SRECs. Additional SRECs from prior years are also eligible for the current compliance period, which may impact the current year’s requirements.

Pennsylvania: The reporting year 2012 requirement for PA equates to retiring approximately 49,450 eligible SRECs. If all compliance obligations were met using 2012 vintage SRECs, approximately 41.2 MW would need to be operational all year long. As of June 11, 2012, 213.2 MW of solar capacity was registered and eligible to create PA compliant SRECs. As of June 11, 2012, PJM GATS reported the issuance of approximately 174,000 PA2012 SRECs. Given the oversupply during previous reporting years, there are also SRECs from the 2010 and 2011 reporting years eligible for the PA2012 compliance period. For an update on HB1580 to increase the Solar RPS requirements, see the following link.

Washington, DC: DC’s 2012 RPS amended solar target requires approximately 61,180 SRECs to be retired by the end of the compliance period. The figures displayed above demonstrate the capacity of systems eligible to create DC SRECs moving forward. These SREC and capacity figures do not take into consideration the amount of electricity delivered into the district that may be exempt from complying with the Distributed Generation Amendment Act increases, considering some electricity contracts may have been signed prior to the amendment’s implementation. As of June 11, 2012, 24.1 MW of capacity was eligible to generate DC SRECs. Additionally, as of June 11, 2012, GATS reported the issuance of approximately 8,600 DC2012 eligible SRECs. SRECs from prior years are also eligible for the current compliance period, which may impact the current year’s requirements.

Massachusetts DOER Qualified Projects

As of June 7, 2012, there were 2,213 MA DOER qualified solar projects; 2,184 operational and 29 not operational. Total qualified capacity is 84.4 MW, 74.2 of which is operational and 10.2 MW not operational. Electricity suppliers providing power to the state need to acquire approximately 73,400 SRECs in 2012. 29,017 MWh have been reported to the PTS during January – May 2012. The next issuance period for Q1 2012 SRECs will be on July 15, 2012.

Capacity Summary By State

The tables above demonstrate the capacity breakout by state. Note, that for all PJM GATS registered projects, each state includes all projects certified to sell into that state. State RPS programs that allow for systems sited in other states to participate have been broken up by systems sited in-state and out-of-state. Additional detail has been provided to demonstrate the total capacity of systems only certified for one specific state market versus being certified for multiple state markets. For example, PA includes projects only certified to sell into the PA SREC market, broken out by in-state and out-of-state systems, as well as projects that are also certified to sell into PA and Other State markets broken out by in state and out of state systems (i.e. OH, DC, MD, DE, NJ). PA Out of State includes systems sited in states with their own state SREC market (i.e. DE) as well as systems sited in states that have no SREC market (i.e. VA). Also, it is important to note that the Current Capacity represents the total megawatts eligible to produce and sell SRECs as of the noted date, while the Estimated Required Capacity – Current and Next Reporting Year represents the estimated number of MW that need to be online on average throughout the reporting period to meet the RPS requirement within each state with only that particular compliance period vintage. For example, New Jersey needs approximately 368 MW online for the entire 2012 reporting year to meet the RPS requirement with 2012 vintage SRECs only. SRECs still available from prior eligible periods can also impact the Solar RPS requirements. Additionally, the data presented above does not include projects that are in the pipeline or currently going through the registration process in each state program. This data represents specifically the projects that have been approved for the corresponding state SREC markets as of the dates noted.

*Source: State of Delaware Pilot Program For the Procurement of Solar Renewable Energy Credits: Recommendations of the Renewable Energy Taskforce

Note: SREC requirements for markets without fixed SREC targets have been forecast based based on EIA Report updated 11/15/11 “By End-Use Sector, by State, by Provider”. Projected SRECs required utilizes the most recent EIA electricity data applying an average 1.5% growth rate per forecast year. The state’s RPS Solar requirement is then multiplied by forecast total electricity sales to arrive at projected SRECs required. Projected capacity required is based on a factor of 1,200 MWh in PJM states and 1,130 MWh in MA, generated per MW of installed capacity per year.

Solar Capacity in the SREC States – April 2012

Posted May 13th, 2012 by SRECTrade.

SRECTrade SREC Markets Report: April 2012

The following post outlines the megawatts of solar capacity certified and/or registered to create SRECs in the Solar REC markets SRECTrade currently serves.

A PDF copy of this table can be found here.

PJM Eligible Systems

As of this writing, there were 24,784 solar PV and 316 solar thermal systems registered and eligible to create SRECs in the PJM Generation Attribute Tracking System (GATS). Of these eligible systems, 147 (0.59%) have a nameplate capacity of 1 megawatt or greater, of which 14 systems are greater than 5 MW. The largest system, the PSE&G utility pole mount project located in New Jersey, is 25.1 MW, and the second largest, located in New Jersey is 12.5 MW. The third largest system, at 12 MW, is located in Ohio.

Delaware: The reporting year 2011-12 (6/1/11 – 5/31/12) requirement for DE equates to approximately 23,700 SRECs being retired. If all retired SRECs were of DE2011-12 vintage, approximately 19.8 MW would need to be operational all year long. As of May 7, 2012, 28.0 MW of solar capacity was registered and eligible to create DE SRECs in PJM GATS. 11.2 MW of the 28.0 MW currently eligible is from the Dover Sun Park project developed by LS Power. In the 2011-12 compliance year, Delmarva Power has contracted to purchase 9,846 SRECs from the project, of which 7,000 are being held by the Sustainable Energy Utility (SEU) until 2015-16*. Additionally, the DE SREC Pilot Program solicitation recently closed its first solicitation. As of May 11, 2012, PJM GATS reported the issuance of approximately 23,400 DE2011-12 vintage SRECs. Additional SRECs from prior eligible periods may also impact the market should there be a demand for these older vintage SRECs.

Maryland: The end of February marked the first issuance period of MD2012 SRECs in PJM GATS. As of May 7, 2012, 45.6 MW of MD sited solar capacity was registered to create MD eligible SRECs. 2012 Solar RPS requirements are estimated at 56.1 MW or approximately 67,310 SRECs. The MD Senate recently passed legislation to pull forward the RPS requirements. As of May 11, 2012, PJM GATS reported the issuance of approximately 10,200 MD2012 SRECs. Additionally, all out of state MD systems are no longer eligible to produce MD certified SRECs and their MD certification numbers have been removed from their systems in PJM GATS. Lastly, there are MD sited SRECs available from prior eligible periods, which could be utilized for compliance needs in 2012.

New Jersey: The New Jersey 2012 reporting year requires 442,000 SRECs to be retired. This equates to approximately 368 MW of capacity being operational all year long, assuming all requirements were met with current vintage year SRECs. As of May 7, 2012, 700.2 MW of solar capacity was registered and eligible to create NJ SRECs in PJM GATS. While this figure represents all projects registered in GATS, there are recently installed projects awaiting issuance of a New Jersey state certification number. This delay results in a portion of installed projects not yet represented in the 700.2 MW figure. As of March 31, 2012 the NJ Office of Clean Energy (NJ OCE) reported that 730.3 MW of solar had been installed in NJ. Additionally, estimates through April 2012 show almost 760 MW of total installed capacity. For additional information on the status of the NJ market and information on the expected legislation to adjust the Solar RPS see the following: New Jersey SREC Market Update May 2012. As of May 11, 2012, PJM GATS reported the issuance of approximately 455,500 NJ2012 SRECs. This figure surpasses the current 2012 compliance year requirement of 442,000 SRECs.

Ohio: Ohio’s 2012 RPS solar target requires approximately 95,300 SRECs to be retired by the end of the compliance period. At least 50% of the SREC requirement must come from systems sited in the state. As of May 7, 2012, 46.8 MW of in-state capacity and 87.3 MW of out-of-state capacity were eligible to generate OH SRECs. A large increase of in state capacity recently came from a 9.8 MW project sited at the Campbell Soup facility in Napoleon, OH. As of May 11, 2012, GATS issued approximately 9,940 in-state and 20,170 out-of-state OH2012 eligible SRECs. Additional SRECs from prior years are also eligible for the current compliance period, which may impact the current year’s requirements.

Pennsylvania: The reporting year 2012 requirement for PA equates to retiring approximately 49,450 eligible SRECs. If all compliance obligations were met using 2012 vintage SRECs, approximately 41.2 MW would need to be operational all year long. As of May 7, 2012, 203.1 MW of solar capacity was registered and eligible to create PA compliant SRECs. As of May 11, 2012, PJM GATS reported the issuance of approximately 144,900 PA2012 SRECs. Given the oversupply during previous reporting years, there are also SRECs from the 2010 and 2011 reporting years eligible for the PA2012 compliance period.

Washington, DC: DC’s 2012 RPS amended solar target requires approximately 61,180 SRECs to be retired by the end of the compliance period. The figures displayed above demonstrate the capacity of systems eligible to create DC SRECs moving forward. These SREC and capacity figures do not take into consideration the amount of electricity delivered into the district that may be exempt from complying with the Distributed Generation Amendment Act increases, considering some electricity contracts may have been signed prior to the amendment’s implementation. As of May 7, 2012, 23.9 MW of capacity was eligible to generate DC SRECs. Additionally, as of May 11, 2012, GATS reported the issuance of approximately 5,800 DC2012 eligible SRECs. SRECs from prior years are also eligible for the current compliance period, which may impact the current year’s requirements.

Massachusetts DOER Qualified Projects

As of May 7, 2012, there were 1,807 MA DOER qualified solar projects; 1,775 operational and 32 not operational. Total qualified capacity is 72.2 MW, 59.5 of which is operational and 12.7 MW not operational. Electricity suppliers providing power to the state need to acquire approximately 62,900 and 73,400 SRECs in 2011 and 2012, respectively. Through the Q4 2011 issuance period (4/15/12), 26,598 SRECs have been minted. Additionally, 20,421 MWh have been reported to the PTS during January – April 2012. Given the SRECs issued through Q4 2011, the 2011 compliance period is short by approximately 36,302. The next issuance period for Q1 2012 SRECs will be on July 15, 2012.

For additional analysis on the current state of the MA SREC market and an outlook on 2012 see the following post published on March 16, 2012: Massachusetts SREC Market Update – March 2012

Capacity Summary By State

The tables above demonstrate the capacity breakout by state. Note, that for all PJM GATS registered projects, each state includes all projects certified to sell into that state. State RPS programs that allow for systems sited in other states to participate have been broken up by systems sited in-state and out-of-state. Additional detail has been provided to demonstrate the total capacity of systems only certified for one specific state market versus being certified for multiple state markets. For example, PA includes projects only certified to sell into the PA SREC market, broken out by in-state and out-of-state systems, as well as projects that are also certified to sell into PA and Other State markets broken out by in state and out of state systems (i.e. OH, DC, MD, DE, NJ). PA Out of State includes systems sited in states with their own state SREC market (i.e. DE) as well as systems sited in states that have no SREC market (i.e. VA). Also, it is important to note that the Current Capacity represents the total megawatts eligible to produce and sell SRECs as of the noted date, while the Estimated Required Capacity – Current and Next Reporting Year represents the estimated number of MW that need to be online on average throughout the reporting period to meet the RPS requirement within each state with only that particular compliance period vintage. For example, New Jersey needs approximately 368 MW online for the entire 2012 reporting year to meet the RPS requirement with 2012 vintage SRECs only. SRECs still available from prior eligible periods can also impact the Solar RPS requirements. Additionally, the data presented above does not include projects that are in the pipeline or currently going through the registration process in each state program. This data represents specifically the projects that have been approved for the corresponding state SREC markets as of the dates noted.

*Source: State of Delaware Pilot Program For the Procurement of Solar Renewable Energy Credits: Recommendations of the Renewable Energy Taskforce

Note: SREC requirements for markets without fixed SREC targets have been forecast based based on EIA Report updated 11/15/11 “By End-Use Sector, by State, by Provider”. Projected SRECs required utilizes the most recent EIA electricity data applying an average 1.5% growth rate per forecast year. The state’s RPS Solar requirement is then multiplied by forecast total electricity sales to arrive at projected SRECs required. Projected capacity required is based on a factor of 1,200 MWh in PJM states and 1,130 MWh in MA, generated per MW of installed capacity per year.

New Jersey SREC Update May 2012

Posted May 7th, 2012 by SRECTrade.

New Jersey SRECs recently traded at $115.16 per SREC in SRECTrade’s May 2012 auction. This follows the dramatic decline in prices that the New Jersey SREC market has experienced since the beginning of the 2012 energy year. Click here for historic data on SRECTrade’s New Jersey SREC market auction pricing.

What’s going on?

The New Jersey SREC market is oversupplied. The state’s  Solar Renewable Portfolio Standard (RPS) targets a fixed number of megawatt hours (MW-hrs) needed to be purchased by electricity suppliers each compliance period. A MW-hr is the equivalent of one SREC, so in NJ we discuss the SREC market both in terms of total capacity installed in MW and total number of SRECs available each year. Under the current RPS, significantly more solar has been installed than is necessary to meet the state’s RPS goals for the next several years.

The 2012 reporting year (June 1, 2011 – May 31, 2012) requires 442,000 SRECs. Our March 2012 capacity analysis (scroll down to see the NJ numbers) shows that as of the beginning of April, total registered installed capacity was 670.9 MW with 386,500 SRECs issued. More recent data from the New Jersey Office of Clean Energy shows the installed capacity, as of March 31, 2012, at 730.3 MW. Additionally, approximately 455,000 SRECs have been issued in GATS from solar PV generation through March 2012. This figure, demonstrates that as of the last issuance period, there are more than enough SRECs available in the market to meet the 2012 reporting year requirement of 442,000 SRECs. The Generation Attribute Tracking System (GATS) is the organization that all New Jersey PV systems must register with in order to create and transact SRECs.

Another factor is that SREC issuance tends to follow a natural lag due to missing meter reading submissions and delays registering systems with GATS.  Given our experience with this data, it’s reasonable to expect a further bump in SREC numbers through March 2012. Also, April and May 2012 SRECs will be issued at the end of May and June, respectively, and will also add to this year’s total SREC issuance figures.

The additional volume to be issued allows us to project that the market is likely 40% to 50% oversupplied for the 2012 energy year. Lastly, when analyzing the 2013 through 2015 energy year current RPS requirements, the figures show that the market will be oversupplied when taking into consideration eligible excess SRECs rolled forward from prior years and the existing amount of installed capacity as of 3/31/12 currently eligible to produce SRECs. The table below demonstrates this in more detail:

Proposals to stabilize the SREC market

Industry stakeholders are working with the New Jersey legislature to come up with a way to stabilize the NJ SREC market. A NJBiz.com article dated May 3rd, mentions a possible bill proposal by Sen. Bob Smith (D-Piscataway), Chairman of the Senate Environment Committee, that would accelerate New Jersey’s solar goals while reducing how much buyers would need to pay for their SRECs if they don’t have enough SRECs in their portfolios at the end of each energy year.

To date, no bill has been made publicly available. Based on the information provided on the NJ State Legislature website, it appears the bill will be slated under the number S1925. The current description listed includes the following, “Revises certain solar renewable energy programs and requirements; provides for aggregating net metering of Class I renewable energy production on certain contiguous and non-contiguous properties owned by local government units and school districts.”

Until then, we must speculate on what the final contents of the bill will be.  An additional consideration is that even if a bill is passed by the NJ legislature, the bill will likely not go into effect until the 2014 energy year which starts in June 2013.

Solar Capacity in the SREC States – March 2012

Posted April 9th, 2012 by SRECTrade.

SRECTrade SREC Markets Report: March 2012

The following post outlines the megawatts of solar capacity certified and/or registered to create SRECs in the Solar REC markets SRECTrade currently serves.

A PDF copy of this table can be found here.

PJM Eligible Systems

As of this writing, there were 23,871 solar PV and 287 solar thermal systems registered and eligible to create SRECs in the PJM Generation Attribute Tracking System (GATS). Of these eligible systems, 139 (0.58%) have a nameplate capacity of 1 megawatt or greater, of which 14 systems are greater than 5 MW. The largest system, the PSE&G utility pole mount project located in New Jersey, is 25.1 MW, and the second largest, located in New Jersey is 12.5 MW. The third largest system, at 12 MW, is located in Ohio.

Delaware: The reporting year 2011-12 (6/1/11 – 5/31/12) requirement for DE equates to approximately 23,700 SRECs being retired. If all retired SRECs were of DE2011-12 vintage, approximately 19.8 MW would need to be operational all year long. As of April 4, 2012, 27.8 MW of solar capacity was registered and eligible to create DE SRECs in PJM GATS. 11.2 MW of the 27.8 MW currently eligible is from the Dover Sun Park project developed by LS Power. In the 2011-12 compliance year, Delmarva Power has contracted to purchase 9,846 SRECs from the project, of which 7,000 are being held by the Sustainable Energy Utility (SEU) until 2015-16*. Additionally, the DE SREC Pilot Program solicitation is under way, with a portion of the capacity tiers already closed. As of April 8, 2012, PJM GATS reported the issuance of approximately 19,600 DE2011-12 vintage SRECs. Additional SRECs from prior eligible periods may also impact the market should there be a demand for these older vintage SRECs.

DE Chart

Maryland: The end of February marked the first issuance period of MD2012 SRECs in PJM GATS. As of April 4, 2012, 44.0 MW of MD sited solar capacity was registered to create MD eligible SRECs. 2012 Solar RPS requirements are estimated at 56.1 MW or approximately 67,310 SRECs. Legislation is making its way through the MD legislature to pull forward the RPS requirements. As of April 8, 2012, PJM GATS reported the issuance of approximately 5,500 MD2012 SRECs. Additionally, all out of state MD systems are no longer eligible to produce MD certified SRECs and their MD certification numbers have been removed from their systems in PJM GATS. Lastly, there are MD sited SRECs available from prior eligible periods, which could be utilized for compliance needs in 2012.

MD Chart

New Jersey: The New Jersey 2012 reporting year requires 442,000 SRECs to be retired. This equates to approximately 368 MW of capacity being operational all year long, assuming all requirements were met with current vintage year SRECs. As of April 4, 2012, 670.9 MW of solar capacity was registered and eligible to create NJ SRECs in PJM GATS. While this figure represents all projects registered in GATS, there are recently installed projects awaiting issuance of a New Jersey state certification number. This delay results in a portion of installed projects not yet represented in the 670.9 MW figure. As of February 29, 2012 the NJ Office of Clean Energy (NJ OCE) reported that 689.1 MW of solar had been installed in NJ. As of April 8, 2012, PJM GATS reported the issuance of approximately 386,500 NJ2012 SRECs.

NJ Chart

Ohio: Ohio’s 2012 RPS solar target requires approximately 95,300 SRECs to be retired by the end of the compliance period. At least 50% of the SREC requirement must come from systems sited in the state. As of April 4, 2012, 44.9 MW of in-state capacity and 84.0 MW of out-of-state capacity were eligible to generate OH SRECs. A large increase of in state capacity recently came from a 9.8 MW project sited at the Campbell Soup facility in Napoleon, OH. As of April 8, 2012, GATS issued approximately 5,200 in-state and 11,200 out-of-state OH2012 eligible SRECs. Additional SRECs from prior years are also eligible for the current compliance period, which may impact the current year’s requirements.

OH Chart

Pennsylvania: The reporting year 2012 requirement for PA equates to retiring approximately 49,450 eligible SRECs. If all compliance obligations were met using 2012 vintage SRECs, approximately 41.2 MW would need to be operational all year long. As of April 4, 2012, 187.9 MW of solar capacity was registered and eligible to create PA compliant SRECs. As of April 8, 2012, PJM GATS reported the issuance of approximately 124,500 PA2012 SRECs. Given the oversupply during previous reporting years, there are also SRECs from the 2010 and 2011 reporting years eligible for the PA2012 compliance period.

PA Chart

Washington, DC: DC’s 2012 RPS amended solar target requires approximately 61,180 SRECs to be retired by the end of the compliance period. The figures displayed above demonstrate the capacity of systems eligible to create DC SRECs moving forward. These SREC and capacity figures do not take into consideration the amount of electricity delivered into the district that may be exempt from complying with the Distributed Generation Amendment Act increases, considering some electricity contracts may have been signed prior to the amendment’s implementation. As of April 4, 2012, 23.1 MW of capacity was eligible to generate DC SRECs. Additionally, as of April 8, 2012, GATS reported the issuance of approximately 3,100 DC2012 eligible SRECs. SRECs from prior years are also eligible for the current compliance period, which may impact the current year’s requirements.

DC Chart

Massachusetts DOER Qualified Projects

As of April 5, 2012, there were 1,728 MA DOER qualified solar projects; 1,698 operational and 30 not operational. Total qualified capacity is 64.1 MW, 53.7 of which is operational and 10.4 not operational. Electricity suppliers providing power to the state need to acquire approximately 62,900 and 73,400 SRECs in 2011 and 2012, respectively. Through the Q3 2011 issuance period (1/15/12), 19,257 SRECs have been minted. Additionally, more than 7,000 MWh have been reported to the PTS during Q4 2011. The Department of Energy Resources (DOER) projects approximately 29,000 SRECs to be generated in 2011, leaving the market short approximately 33,900 SRECs. The next issuance period for Q4 2011 SRECs will be on April 15, 2012.

MA Chart

For additional analysis on the current state of the MA SREC market and an outlook on 2012 see the following post published on March 16, 2012: Massachusetts SREC Market Update – March 2012

Capacity Summary By State

The tables above demonstrate the capacity breakout by state. Note, that for all PJM GATS registered projects, each state includes all projects certified to sell into that state. State RPS programs that allow for systems sited in other states to participate have been broken up by systems sited in-state and out-of-state. Additional detail has been provided to demonstrate the total capacity of systems only certified for one specific state market versus being certified for multiple state markets. For example, PA includes projects only certified to sell into the PA SREC market, broken out by in-state and out-of-state systems, as well as projects that are also certified to sell into PA and Other State markets broken out by in state and out of state systems (i.e. OH, DC, MD, DE, NJ). PA Out of State includes systems sited in states with their own state SREC market (i.e. DE) as well as systems sited in states that have no SREC market (i.e. VA). Also, it is important to note that the Current Capacity represents the total megawatts eligible to produce and sell SRECs as of the noted date, while the Estimated Required Capacity – Current and Next Reporting Year represents the estimated number of MW that need to be online on average throughout the reporting period to meet the RPS requirement within each state. For example, New Jersey needs approximately 368 MW online for the entire 2012 reporting year to meet the RPS requirement. Additionally, the data presented above does not include projects that are in the pipeline or currently going through the registration process in each state program. This data represents specifically the projects that have been approved for the corresponding state SREC markets as of the dates noted.

*Source: State of Delaware Pilot Program For the Procurement of Solar Renewable Energy Credits: Recommendations of the Renewable Energy Taskforce

Note: SREC requirements for markets without fixed SREC targets have been forecast based based on EIA Report updated 11/15/11 “By End-Use Sector, by State, by Provider”. Projected SRECs required utilizes the most recent EIA electricity data applying an average 1.5% growth rate per forecast year. The state’s RPS Solar requirement is then multiplied by forecast total electricity sales to arrive at projected SRECs required. Projected capacity required is based on a factor of 1,200 MWh in PJM states and 1,130 MWh in MA, generated per MW of installed capacity per year.

Solar Capacity in the SREC States – February 2012

Posted March 8th, 2012 by SRECTrade.

SRECTrade SREC Markets Report: February 2012

The following post outlines the megawatts of solar capacity certified and/or registered to create SRECs in the Solar REC markets SRECTrade currently serves.

A PDF copy of this table can be found here.

Renewable Generators in GATS 3_7_12

PJM Eligible Systems

As of this writing, there were 23,036 solar PV and 272 solar thermal systems registered and eligible to create SRECs in the PJM Generation Attribute Tracking System (GATS). Of these eligible systems, 133 (0.57%) have a nameplate capacity of 1 megawatt or greater, of which 14 systems are greater than 5 MW. The largest system, the PSE&G utility pole mount project located in New Jersey, is 25.1 MW, and the second largest, located in Ohio is 12 MW. The third largest system, at 11.2 MW, is located in Delaware.

Delaware: The reporting year 2011-12 (6/1/11 – 5/31/12) requirement for DE equates to approximately 23,700 SRECs being retired. If all retired SRECs were of DE2011-12 vintage, approximately 19.8 MW would need to be operational all year long. As of March 7, 2012, 27.1 MW of solar capacity was registered and eligible to create DE SRECs in PJM GATS. 11.2 MW of the 27.1 MW currently eligible is from the Dover Sun Park project developed by LS Power. In the 2011-12 compliance year, Delmarva Power has contracted to purchase 9,846 SRECs from the project, of which 7,000 are being held by the Sustainable Energy Utility (SEU) until 2015-16*. As of March 8, 2012, PJM GATS reported the issuance of approximately 17,300 DE2011-12 vintage SRECs. Additional SRECs from prior eligible periods may also impact the market should there be a demand for these older vintage SRECs.

DE Chart

Maryland: Maryland’s 2011 solar compliance requirements are currently being finalized. The 2011 Solar RPS target requires approximately 33,160 SRECs to be retired. To meet this using only 2011 vintage SRECs, approximately 27.6 MW would need to be operational all year long. The MD Public Services Commission recently announced that enough solar facilities were connected to the Maryland electric grid to satisfy the 2011 Solar RPS requirements with MD sited SRECs. The end of February marked the first issuance period of MD2012 SRECs in PJM GATS. As of March 7, 2012, 41.8 MW of MD sited solar capacity was registered to create MD eligible SRECs. 2012 Solar RPS requirements are estimated at 56.1 MW or approximately 67,310 SRECs. As of  March 8, 2012, PJM GATS reported the issuance of approximately 2,340 MD2012 SRECs. Additionally, all out of state MD systems are no longer eligible to produce MD certified SRECs and their MD certification numbers have been removed from their systems in PJM GATS. Lastly, there are MD sited SRECs available from prior eligible periods, which could be utilized for compliance needs in 2012.

MD Chart

New Jersey: The New Jersey 2012 reporting year requires 442,000 SRECs to be retired. This equates to approximately 368 MW of capacity being operational all year long, assuming all requirements were met with current vintage year SRECs. As of March 7, 2012, 637.1 MW of solar capacity was registered and eligible to create NJ SRECs in PJM GATS. While this figure represents all projects registered in GATS, there are recently installed projects awaiting issuance of a New Jersey state certification number. This delay results in a portion of installed projects not yet represented in the 637.1 MW figure. As of January 31, 2012 the NJ Office of Clean Energy (NJ OCE) reported that 649.2 MW of solar had been installed in NJ. Additionally, preliminary figures from the NJ OCE estimate another 39 MW installed in February 2012, totaling 689 MW of capacity. As of March 8, 2012, PJM GATS reported the issuance of approximately 327,000 NJ2012 SRECs.

NJ Chart

Ohio: Ohio’s 2012 RPS solar target requires approximately 95,300 SRECs to be retired by the end of the compliance period. At least 50% of the SREC requirement must come from systems sited in the state. As of March 7, 2012, 44.0 MW of in-state capacity and 81.3 MW of out-of-state capacity were eligible to generate OH SRECs. A large increase of in state capacity recently came from a 9.8 MW project sited at the Campbell Soup facility in Napoleon, OH. As of March 8, 2012, GATS issued approximately 1,904 in-state and 4,485 out-of-state OH2012 eligible SRECs. Additional SRECs from prior years are also eligible for the current compliance period, which may impact the current year’s requirements.

OH Chart

Pennsylvania: The reporting year 2012 requirement for PA equates to retiring approximately 49,450 eligible SRECs. If all compliance obligations were met using 2012 vintage SRECs, approximately 41.2 MW would need to be operational all year long. As of March 7, 2012, 182.0 MW of solar capacity was registered and eligible to create PA compliant SRECs. As of March 8, 2012, PJM GATS reported the issuance of approximately 115,700 PA2012 SRECs. Given the oversupply during previous reporting years, there are also SRECs from the 2010 and 2011 reporting years eligible for the PA2012 compliance period.

PA Chart

Washington, DC: DC’s 2012 RPS amended solar target requires approximately 61,180 SRECs to be retired by the end of the compliance period. The figures displayed above demonstrate the capacity of systems eligible to create DC SRECs moving forward. These SREC and capacity figures do not take into consideration the amount of electricity delivered into the district that may be exempt from complying with the Distributed Generation Amendment Act increases, considering some electricity contracts may have been signed prior to the amendment’s implementation. As of March 8, 2012, 23.1 MW of capacity was eligible to generate DC SRECs. Additionally, as of March 8, 2012, GATS reported the issuance of approximately 1,320 DC2012 eligible SRECs. SRECs from prior years are also eligible for the current compliance period, which may impact the current year’s requirements.

DC Chart

Massachusetts DOER Qualified Projects

For a additional analysis on the current state of the MA SREC market see the following post published on March 16, 2012: Massachusetts SREC Market Update – March 2012

As of March 6, 2012, there were 1,704 MA DOER qualified solar projects; 1,671 operational and 33 not operational. Total qualified capacity is 63.6 MW, 52.6 of which is operational and 11.0 not operational. Electricity suppliers providing power to the state need to acquire approximately 62,900 and 73,400 SRECs in 2011 and 2012, respectively. Through the Q3 2011 issuance period (1/15/12), 19,257 SRECs have been minted. Additionally, more than 7,000 MWh have been reported to the PTS during Q4 2011. The Department of Energy Resources (DOER) projects approximately 29,000 SRECs to be generated in 2011, leaving the market short approximately 33,900 SRECs. The next issuance period for Q4 2011 SRECs will be on April 15, 2012.

MA Chart

Capacity Summary By State

The tables above demonstrate the capacity breakout by state. Note, that for all PJM GATS registered projects, each state includes all projects certified to sell into that state. State RPS programs that allow for systems sited in other states to participate have been broken up by systems sited in-state and out-of-state. Additional detail has been provided to demonstrate the total capacity of systems only certified for one specific state market versus being certified for multiple state markets. For example, PA includes projects only certified to sell into the PA SREC market, broken out by in-state and out-of-state systems, as well as projects that are also certified to sell into PA and Other State markets broken out by in state and out of state systems (i.e. OH, DC, MD, DE, NJ). PA Out of State includes systems sited in states with their own state SREC market (i.e. DE) as well as systems sited in states that have no SREC market (i.e. VA). Also, it is important to note that the Current Capacity represents the total megawatts eligible to produce and sell SRECs as of the noted date, while the Estimated Required Capacity – Current and Next Reporting Year represents the estimated number of MW that need to be online on average throughout the reporting period to meet the RPS requirement within each state. For example, New Jersey needs approximately 368 MW online for the entire 2012 reporting year to meet the RPS requirement. Additionally, the data presented above does not include projects that are in the pipeline or currently going through the registration process in each state program. This data represents specifically the projects that have been approved for the corresponding state SREC markets as of the dates noted.

*Source: State of Delaware Pilot Program For the Procurement of Solar Renewable Energy Credits: Recommendations of the Renewable Energy Taskforce

Note: SREC requirements for markets without fixed SREC targets have been forecast based based on EIA Report updated 11/15/11 “By End-Use Sector, by State, by Provider”. Projected SRECs required utilizes the most recent EIA electricity data applying an average 1.5% growth rate per forecast year. The state’s RPS Solar requirement is then multiplied by forecast total electricity sales to arrive at projected SRECs required. Projected capacity required is based on a factor of 1,200 MWh in PJM states and 1,130 MWh in MA, generated per MW of installed capacity per year.

Solar Capacity in the SREC States – January 2012

Posted February 8th, 2012 by SRECTrade.

SRECTrade SREC Markets Report: January 2012

The following post outlines the megawatts of solar capacity certified and/or registered to create SRECs in the Solar REC markets SRECTrade currently serves.

A PDF copy of this table can be found here.

GATS Renewable Energy Generators 2_6_12_v1

PJM Eligible Systems

As of this writing, there were 22,172 solar PV and 285 solar thermal systems registered and eligible to create SRECs in the PJM Generation Attribute Tracking System (GATS). Of these eligible systems, 109 (0.49%) have a nameplate capacity of 1 megawatt or greater, of which 11 systems are greater than 5 MW. The largest system, the PSE&G utility pole mount project located in New Jersey, is 25.1 MW, and the second largest, located in Ohio is 12 MW. The third largest system, at 11.2 MW, is located in Delaware.

Delaware: The reporting year 2011-12 (6/1/11 – 5/31/12) requirement for DE equates to approximately 23,700 SRECs being retired. If all retired SRECs were of DE2011-12 vintage, approximately 19.8 MW would need to be operational all year long. As of February 6, 2012, 26.1 MW of solar capacity was registered and eligible to create DE SRECs in PJM GATS. 11.2 MW of the 26.1 MW currently eligible is from the Dover Sun Park project developed by LS Power. In the 2011-12 compliance year, Delmarva Power has contracted to purchase 9,846 SRECs from the project, of which 7,000 are being held by the Sustainable Energy Utility (SEU) until 2015-16*. As of February 7, 2012, PJM GATS reported the issuance of approximately 15,500 DE2011-12 vintage SRECs. Additional SRECs from prior eligible periods may also impact the market should there be a demand for these older vintage SRECs.

DE chart

Maryland: Maryland’s 2011 Solar RPS target requires approximately 33,160 SRECs to be retired. To meet this using only 2011 vintage SRECs, approximately 27.6 MW would need to be operational all year long. As of February 6, 2012, 63.9 MW of solar capacity was registered to create MD eligible SRECs. 39.2 MW of this capacity was sited in the state of MD. The RPS currently requires electricity suppliers to acquire SRECs from in-state sited solar systems before looking to outside systems. As of February 7, 2012, PJM GATS reported the issuance of approximately 34,100 MD2011 SRECs from MD sited systems. There are also MD sited SRECs available from prior eligible periods, which could be utilized for compliance needs in 2011.

MD Chart

New Jersey: The New Jersey 2012 reporting year requires 442,000 SRECs to be retired. This equates to approximately 368 MW of capacity being operational all year long if all requirements were met with current vintage year SRECs. As of February 6, 2012, 535.2 MW of solar capacity was registered and eligible to create NJ SRECs in PJM GATS. While this figure represents all projects registered in GATS, there are recently installed projects awaiting issuance of a New Jersey state certification number. This delay results in a portion of installed projects not yet represented in the 535.2 MW figure. As of December 31, 2011 the NJ Office of Clean Energy (NJ OCE) reported that 565.9 MW of solar had been installed in NJ. As of February 7, 2012, PJM GATS reported the issuance of approximately 282,500 NJ2012 SRECs.

NJ Chart

Ohio: Ohio’s 2011 RPS solar target requires approximately 46,940 SRECs to be retired by the end of the compliance period. At least 50% of the SREC requirement must come from systems sited in the state. As of February 6, 2012, 43.1 MW of in-state capacity and 76.7 MW of out-of-state capacity were eligible to generate OH SRECs. A large increase of in state capacity came from a 9.8 MW project sited at the Campbell Soup facility in Napoleon, OH. Additionally, as of February 7, 2012, GATS issued approximately 30,230 in-state and 71,000 out-of-state OH2011 eligible SRECs. Additional SRECs from prior years are also eligible for the current compliance period, which may impact the current year’s requirements.

OH Chart

Pennsylvania: The reporting year 2012 requirement for PA equates to retiring approximately 49,450 eligible SRECs. If all compliance obligations were met using 2012 vintage SRECs, approximately 41.2 MW would need to be operational all year long. As of February 6, 2012, 167.6 MW of solar capacity was registered and eligible to create PA compliant SRECs. As of February 7, 2012, PJM GATS reported the issuance of approximately 105,000 PA2012 SRECs. Given the oversupply during previous reporting years, there are also SRECs from the 2010 and 2011 reporting years eligible for the PA2012 compliance period.

PA chart

Washington, DC: DC’s 2011 RPS amended solar target requires approximately 48,220 SRECs to be retired by the end of the compliance period. The figures displayed above demonstrate the capacity of systems eligible to create DC SRECs moving forward. These SREC and capacity figures do not take into consideration the amount of electricity delivered into the district that may be exempt from complying with the Distributed Generation Amendment Act increases, considering some electricity contracts may have been signed prior to the amendment’s implementation. As of February 6, 2012, 23.0 MW of capacity was eligible to generate DC SRECs. Additionally, as of February 7, 2012, GATS issued approximately 23,800 DC2011 eligible SRECs. SRECs from prior years are also eligible for the current compliance period, which may impact the current year’s requirements.

DC Chart

Massachusetts DOER Qualified Projects

As of January 25, 2012, there were 1,321 MA DOER qualified solar projects; 1,278 operational and 43 not operational. Total qualified capacity is 53.3 MW, 36.7 of which is operational and 16.6 not operational. Of these qualified systems, 12 (0.91%) have a nameplate capacity of 1 megawatt or greater, of which 4 are between 1.5 and 2 MW. Four of the projects greater than 1 MW are currently operational, with the largest, 2.3 MW, recently operational as of December 2011. Electricity suppliers providing power to the state need to acquire approximately 62,900 SRECs in 2011. Through the Q3 2011 issuance period (1/15/12), 19,257 SRECs have been minted. The Department of Energy Resources (DOER) projects approximately 29,000 SRECs to be generated in 2011, leaving the market short approximately 33,900 SRECs. The next issuance period for Q4 2011 SRECs will be on April 15, 2012.

MA Chart

Capacity Summary By State

The tables above demonstrate the capacity breakout by state. Note, that for all PJM GATS registered projects, each state includes all projects certified to sell into that state. State RPS programs that allow for systems sited in other states to participate have been broken up by systems sited in-state and out-of-state. Additional detail has been provided to demonstrate the total capacity of systems only certified for one specific state market versus being certified for multiple state markets. For example, PA includes projects only certified to sell into the PA SREC market, broken out by in-state and out-of-state systems, as well as projects that are also certified to sell into PA and Other State markets broken out by in state and out of state systems (i.e. OH, DC, MD, DE, NJ). PA Out of State includes systems sited in states with their own state SREC market (i.e. DE) as well as systems sited in states that have no SREC market (i.e. VA). Also, it is important to note that the Current Capacity represents the total megawatts eligible to produce and sell SRECs as of the noted date, while the Estimated Required Capacity – Current and Next Reporting Year represents the estimated number of MW that need to be online on average throughout the reporting period to meet the RPS requirement within each state. For example, New Jersey needs approximately 368 MW online for the entire 2012 reporting year to meet the RPS requirement. Additionally, the data presented above does not include projects that are in the pipeline or currently going through the registration process in each state program. This data represents specifically the projects that have been approved for the corresponding state SREC markets as of the dates noted.

*Source: State of Delaware Pilot Program For the Procurement of Solar Renewable Energy Credits: Recommendations of the Renewable Energy Taskforce

Note: SREC requirements for markets without fixed SREC targets have been forecast based based on EIA Report updated 11/15/11 “By End-Use Sector, by State, by Provider”. Projected SRECs required utilizes the most recent EIA electricity data applying an average 1.5% growth rate per forecast year. The state’s RPS Solar requirement is then multiplied by forecast total electricity sales to arrive at projected SRECs required. Projected capacity required is based on a factor of 1,200 MWh in PJM states and 1,130 MWh in MA, generated per MW of installed capacity per year.

Solar Capacity in the SREC States – December 2011

Posted December 28th, 2011 by SRECTrade.

SRECTrade SREC Markets Report: December 2011

The following post outlines the megawatts of solar capacity certified and/or registered to create SRECs in the Solar REC markets SRECTrade currently serves.

A PDF copy of this table can be found here.

Capacity_December2011

PJM Eligible Systems

As of the end of December, there were 20,967 solar PV and 252 solar thermal systems registered and eligible to create SRECs in the PJM Generation Attribute Tracking System (GATS). Of these eligible systems, 95 (0.45%) have a nameplate capacity of 1 megawatt or greater, of which 10 systems are greater than 5 MW. The largest system, currently located in New Jersey, is 18.3 MW, and the second largest, located in Ohio is 12 MW. The third largest system, at 11.2 MW, is located in Delaware.

Delaware: The reporting year 2011-12 (6/1/11 – 5/31/12) requirement for DE equates to approximately 23,700 SRECs being retired. If all retired SRECs were of DE2011-12 vintage, approximately 19.8 MW would need to be operational all year long. As of December 27, 2011, 25.5 MW of solar capacity was registered and eligible to create DE SRECs in PJM GATS. 11.2 MW of the 25.5 MW currently eligible is from the Dover Sun Park project developed by LS Power. In the 2011-12 compliance year, Delmarva Power has contracted to purchase 9,846 SRECs from the project, of which 7,000 are being held by the Sustainable Energy Utility (SEU) until 2015-16*. As of January 3, 2012, PJM GATS reported the issuance of approximately 13,560 DE2011-12 vintage SRECs. Additional SRECs from prior eligible periods may also impact the market should there be a demand for these older vintage SRECs.

DE Chart

Maryland: Maryland’s 2011 Solar RPS target requires approximately 33,160 SRECs to be retired. To meet this using only 2011 vintage SRECs, approximately 27.6 MW would need to be operational all year long. As of December 27, 2011, 62.0 MW of solar capacity was registered to create MD eligible SRECs. 37.8 MW of this capacity was sited in the state of MD. The RPS currently requires electricity suppliers to acquire SRECs from in-state sited solar systems before looking to outside systems. As of January 3, 2012, PJM GATS reported the issuance of approximately 29,000 MD2011 SRECs from MD sited systems. There are also MD sited SRECs available from prior eligible periods, which could be utilized for compliance needs in 2011.

MD Chart

New Jersey: The New Jersey 2012 reporting year requires 442,000 SRECs to be retired. This equates to approximately 368 MW of capacity being operational all year long. As of December 27, 2011, 483.2 MW of solar capacity was registered and eligible to create NJ SRECs in PJM GATS. While this figure represents all projects registered in GATS, there are recently installed projects awaiting issuance of a New Jersey state certification number. This delay results in a portion of installed projects not yet represented in the 483.2 MW figure. As of November 30, 2011 the NJ Office of Clean Energy (NJ OCE) reported that 531.7 MW of solar had been installed in NJ. As of January 3, 2012, PJM GATS reported the issuance of approximately 240,800 NJ2012 SRECs.

NJ Chart_v2

Ohio: Ohio’s 2011 RPS solar target requires approximately 46,940 SRECs to be retired by the end of the compliance period. At least 50% of the SREC requirement must come from systems sited in the state. As of December 27, 2011, 29.0 MW of in-state capacity and 68.0 MW of out-of-state capacity were eligible to generate OH SRECs. Additionally, as of January 3, 2012, GATS issued approximately 28,180 in-state and 60,580 out-of-state OH2011 eligible SRECs. Additional SRECs from prior years are also eligible for the current compliance period, which may impact the current year’s requirements.

OH Chart

Pennsylvania: The reporting year 2012 requirement for PA equates to retiring approximately 49,450 eligible SRECs. If all compliance obligations were met using 2012 vintage SRECs, approximately 41.2 MW would need to be operational all year long. As of December 27, 2011, 158.3 MW of solar capacity was registered and eligible to create PA compliant SRECs. As January 3, 2012, PJM GATS reported the issuance of approximately 93,370 PA2012 SRECs. Given the oversupply during previous reporting years, there are also SRECs from the 2010 and 2011 reporting years eligible for the PA2012 compliance period.

PA Chart

Washington, DC: DC’s 2011 RPS amended solar target requires approximately 48,220 SRECs to be retired by the end of the compliance period. The figures displayed above demonstrate the capacity of systems eligible to create DC SRECs moving forward. These SREC and capacity figures do not take into consideration the amount of electricity delivered into the district that may be exempt from complying with the Distributed Generation Amendment Act increases, considering some electricity contracts may have been signed prior to the amendment’s implementation. As of December 27, 2011, 21.7 MW of capacity was eligible to generate DC SRECs. Additionally, as if January 3, 2012, GATS issued approximately 21,800 DC2011 eligible SRECs. SRECs from prior years are also eligible for the current compliance period, which may impact the current year’s requirements.

DC Chart

Massachusetts DOER Qualified Projects

As of December 22, 2011, there were 1,264 MA DOER qualified solar projects; 1,244 operational and 20 not operational. Of these qualified systems, 11 (0.9%) have a nameplate capacity of 1 megawatt or greater, of which only 3 are between 1.5 and 2 MW. Three of the projects greater than 1 MW are currently operational. Electricity suppliers providing power to the state need to acquire approximately 62,900 SRECs in 2011. Through the Q2 2011 issuance period (10/15/11), 9,499 SRECs have been minted. The Department of Energy Resources (DOER) projects approximately 29,000 SRECs to be generated this year, leaving the market short approximately 33,900 SRECs. The next issuance period for Q3 2011 SRECs will be on January 15, 2012.

MA Chart

Capacity Summary By State

The tables above demonstrate the capacity breakout by state. Note, that for all PJM GATS registered projects, each state includes all projects certified to sell into that state. State RPS programs that allow for systems sited in other states to participate have been broken up by systems sited in-state and out-of-state. Additional detail has been provided to demonstrate the total capacity of systems only certified for one specific state market versus being certified for multiple state markets. For example, PA includes projects only certified to sell into the PA SREC market, broken out by in-state and out-of-state systems, as well as projects that are also certified to sell into PA and Other State markets broken out by in state and out of state systems (i.e. OH, DC, MD, DE, NJ). PA Out of State includes systems sited in states with their own state SREC market (i.e. DE) as well as systems sited in states that have no SREC market (i.e. VA). Also, it is important to note that the Current Capacity represents the total megawatts eligible to produce and sell SRECs as of the noted date, while the Estimated Required Capacity – Current and Next Reporting Year represents the estimated number of MW that need to be online on average throughout the reporting period to meet the RPS requirement within each state. For example, New Jersey needs approximately 368 MW online for the entire 2012 reporting year to meet the RPS requirement. Additionally, the data presented above does not include projects that are in the pipeline or currently going through the registration process in each state program. This data represents specifically the projects that have been approved for the corresponding state SREC markets as of the dates noted.

*Source: State of Delaware Pilot Program For the Procurement of Solar Renewable Energy Credits: Recommendations of the Renewable Energy Taskforce

Note: SREC requirements for markets without fixed SREC targets have been forecast based based on EIA Report updated 11/15/11 “By End-Use Sector, by State, by Provider”. Projected SRECs required utilizes the most recent EIA electricity data applying an average 1.5% growth rate per forecast year. The state’s RPS Solar requirement is then multiplied by forecast total electricity sales to arrive at projected SRECs required. Projected capacity required is based on a factor of 1,200 MWh in PJM states and 1,130 MWh in MA, generated per MW of installed capacity per year.

Hearing on Pennsylvania SREC Bill (HB 1580) delayed again

Posted December 7th, 2011 by SRECTrade.

A critical Pennsylvania House Consumer Affairs Committee hearing on the Pennsylvania Solar Jobs Bill (HB 1580) scheduled for Thursday, December 8th was delayed again, according to a news flier sent out by the Pennsylvania advocacy group PennFuture. This is the 2nd time that the hearing has been delayed in as many weeks. According to the PennFuture flier, the bill hearing was delayed due to a death in Committee Chair Rep. Godshall’s family. No reschedule date has been announced yet.

Solar Capacity in the SREC States – November 2011

Posted November 29th, 2011 by SRECTrade.

SRECTrade SREC Markets Report: November 2011

The following post outlines the megawatts of solar capacity certified and/or registered to create SRECs in the Solar REC markets SRECTrade currently serves.

A PDF copy of this table can be found here.

GATS_generators_11_28_11

PJM Eligible Systems

As of the end of November, there were 20,223 solar PV and 252 solar thermal systems registered and eligible to create SRECs in the PJM Generation Attribute Tracking System (GATS) registry. Of these eligible systems, 87 (0.42%) have a nameplate capacity of 1 megawatt or greater, of which only 6 systems are greater than 5 MW. The largest system, currently located in New Jersey, is 18.3 MW, and the second largest, located in Ohio is 12 MW. The third largest system, at 11.2 MW, is located in Delaware.

Delaware: The reporting year 2011-2012 requirement for DE equates to approximately 23,340 SRECs being retired. If all retired SRECs were of DE2011-2012 vintage, approximately 19.5 MW would need to be operational all year long. As of November 28, 2011, 22.8 MW of solar capacity was registered and eligible to create DE SRECs in PJM GATS. 11.2 MW of the 22.7 MW currently eligible is from the Dover Sun Park project developed by LS Power. In the 2011-12 compliance year, Delmarva Power has contracted to purchase 9,846 SRECs from the project, of which 7,000 are being held by the Sustainable Energy Utility (SEU) until 2015-16*. As of this writing, PJM GATS reported the issuance of 8,758 DE2011-2012 SRECs. Additional SRECs from the DE2010-2011 period may also impact the market should there be a demand for these older vintage SRECs.

Maryland: Maryland’s 2011 Solar RPS target requires approximately 32,240 SRECs to be retired. To meet this using only 2011 vintage SRECs, approximately 26.9 MW would need to be operational all year long. As of November 28, 2011, 54.8 MW of solar capacity was registered to create MD eligible SRECs. 33.5 MW of this capacity was sited in the state of MD. The RPS currently requires electricity suppliers to acquire SRECs from in-state sited solar systems before looking to outside systems. As of this writing, PJM GATS reported the issuance of 23,439 MD2011 SRECs from MD sited systems. There are also MD sited SRECs available from 2010, which could be utilized for compliance needs in 2011.

New Jersey: The New Jersey 2012 reporting year requires 442,000 SRECs to be retired. This equates to approximately 368 MW of capacity being operational all year long. Given the shortage of NJ2011 Solar RECs, older vintage SRECs will not impact the 2012 market. As of November 28, 2011, 433.2 MW of solar capacity was registered and eligible to create NJ SRECs in PJM GATS. While this figure represents all projects registered in GATS, there are recently installed projects awaiting issuance of a New Jersey state certification number. This delay results in a portion of installed projects not yet represented in the 433.2 MW figure. As of September 30, 2011 the NJ Office of Clean Energy (NJ OCE) reported that 447.7 MW of solar had been installed in NJ. For more details on the increase in NJ capacity see this post. As of this writing, PJM GATS reported the issuance of 163,507 NJ2012 SRECs.

Ohio: Ohio’s 2011 RPS solar target requires approximately 45,210 SRECs to be retired by the end of the compliance period. At least 50% of the SREC requirement must come from systems sited in the state. As of November 28, 2011, 27.7 MW of in-state capacity and 61.3 MW of out-of-state capacity were eligible to generate OH SRECs. Additionally, for the year to date, GATS has issued 23,834 in-state and 47,137 out-of-state OH2011 eligible SRECs. Additional SRECs from prior years are also eligible for the current compliance period, which may impact the current year’s requirements.

OH Capacity Chart

Pennsylvania: The reporting year 2012 requirement for PA equates to retiring approximately 48,430 eligible SRECs. If all compliance obligations were met using 2012 vintage SRECs, approximately 41.9 MW would need to be operational all year long. As of November 28, 2011, 152 MW of solar capacity was registered and eligible to create PA compliant SRECs. As of this writing, PJM GATS reported the issuance of 66,243 PA2012 SRECs. Given the oversupply during previous reporting years, there are also PA2012 eligible SRECs from the 2010 and 2011 reporting years.

Washington, DC: DC’s 2011 RPS amended solar target requires approximately 50,270 SRECs to be retired by the end of the compliance period. The figures displayed above demonstrate the capacity of systems eligible to create DC SRECs moving forward. These figures do not take into consideration the amount of electricity delivered into the district that may be exempt from complying with the Distributed Generation Amendment Act increases, considering some electricity contracts may have been signed prior to the amendment’s implementation. As of November 28, 2011, 21.5 MW of capacity was eligible to generate DC SRECs. Additionally, for the year to date, GATS has issued 18,382 DC2011 eligible SRECs. Additional SRECs from prior years are also eligible for the current compliance period, which may impact the current year’s requirements.

Massachusetts DOER Qualified Projects

As of November 21, 2011, there were 1,149 MA DOER qualified solar projects; 1,128 operational and 21 not operational. Of these qualified systems, 11 (1.0%) have a nameplate capacity of 1 megawatt or greater, of which only 3 are between 1.5 and 2 MW. Three of the projects greater than 1 MW are currently operational. Electricity suppliers providing power to the state need to acquire approximately 62,900 SRECs in 2011. Through the Q2 2011 issuance period (10/15/11), 9,499 SRECs have been minted. The Department of Energy Resources (DOER) projects approximately 29,000 SRECs to be generated this year, leaving the market short approximately 33,900 SRECs.

MA Capacity Chart

Capacity Summary By State

The tables above demonstrate the capacity breakout by state. Note, that for all PJM GATS registered projects, each state includes all projects certified to sell into that state. State RPS programs that allow for systems sited in other states to participate have been broken up by systems sited in-state and out-of-state. Additional detail has been provided to demonstrate the total capacity of systems only certified for one specific state market versus being certified for multiple state markets. For example, PA includes projects only certified to sell into the PA SREC market, broken out by in state and out of state systems, as well as projects that are also certified to sell into PA and Other State markets broken out by in state and out of state systems (i.e. OH, DC, MD, DE, NJ). PA Out of State includes systems sited in states with their own state SREC market (i.e. DE) as well as systems sited in states that have no SREC market (i.e. VA). Also, it is important to note that the Current Capacity represents the total megawatts eligible to produce and sell SRECs as of the noted date, while the Estimated Required Capacity – Current and Next Reporting Year represents the estimated number of MW that need to be online on average throughout the reporting period to meet the RPS requirement within each state. For example, New Jersey needs approximately 368 MW online for the entire 2012 reporting year to meet the RPS requirement. Additionally, the data presented above does not include projects that are in the pipeline or currently going through the registration process in each state program. This data represents specifically the projects that have been approved for the corresponding state SREC markets as of the dates noted.

*Source: State of Delaware Pilot Program For the Procurement of Solar Renewable Energy Credits: Recommendations of the Renewable Energy Taskforce

Note: SREC requirements for markets without fixed SREC targets have been forecast based based on EIA Report “By End-Use Sector, by State, by Provider”. Projected SRECs required utilizes the most recent EIA electricity data applying an average 1.5% growth rate per forecast year. The state’s RPS Solar requirement is then multiplied by forecast total electricity sales to arrive at projected SRECs required. Projected capacity required is based on a factor of 1,200 MWh in PJM states and 1,130 MWh in MA, generated per MW of installed capacity per year.

New Jersey Capacity Update – Solar Continues to Push Forward

Posted November 28th, 2011 by SRECTrade.

NJ2012 Capacity Update

The New Jersey Office of Clean Energy (NJ OCE) published an updated installed solar projects list as of September 30, 2011. According to the NJ OCE, as of 9/30/11 the Garden State installed 447.7 MW of solar capacity. This equates to more than 20 MW added in the month of September, putting the state at an average of 27.1 MW per month and a total of 108.2 MW installed for the 2012 compliance year to date. NJ OCE estimates for October 2012 expect 44 MW of additional capacity to be installed, bringing total installed capacity to over 491 MW.

Although the NJ OCE reports 447.7 MW installed as of September 30, 2011, PJM GATS currently shows 431.2 MW registered to produce SRECs as of 11/26/11. It is common to see a difference in registered projects between the NJ OCE and PJM GATS reported figures as there is typically a delay from when systems are interconnected and installed to when they receive their NJ state certification number and become registered in GATS.

New Jersey’s 2012 reporting year solar requirement is currently set at 442,000 MWhs. Assuming a production factor 1.2 MWh per installed kW per year, the state needs approximately 370 MW operational all year long. As of 11/26/11, GATS has reported 163,507 SRECs issued through September 2011 generation. October 2011 generation will be issued on November 30, 2011. Given the volume issued through September 2011, approximately 37% of the required volume has been generated. This leaves a need of approximately 278,500 SRECs to meet the 442,000 MWh RY2012 target.

Monthly Capacity Analysis_v2-1

Assuming all NJ solar facilities produce at a 1.2 MWh production factor per kW per year, and all systems noted as installed on the NJ OCE installed project list received generation credit from their first full month of operation, the existing installed capacity of 447.7 MW will produce approximately 338,400* SRECs between October 2011 and May 2012. This additional generation will bring the NJ2012 SREC issuance total to approximately 501,900 SRECs, an excess of 60,000 MWhs. Assuming the October 2012 estimates are accurate, the additional of 44 MW in October creates additional oversupply, equating to a forecast of almost 530,600* NJ2012 SRECs minted and an excess of 88,600 MWh. Both of these scenarios only account for the existing installed capacity through September 2011 and estimates through October 2011. Additional supply will continue to come online through the remaining months of NJ2012, with more capacity anticipated to be pushed through at the end of the 2011 calendar year due to the expected expiration of the federal grant incentive. The additional supply coming online throughout the remaining months of NJ2012 will further impact the long SREC market NJ is facing and have an effect on the 2013 market.

NJ2013 SREC Market

As it currently stands, the NJ2013 (June 2012 – May 2013) Renewable Portfolio Standard (RPS) requires 596,000 MWhs of solar generation. This Solar REC requirement equals approximately 496.7 MW to be operational all year long, assuming the NJ2013 requirements are met only using 2013 vintage SRECs. Given the current market, and expected oversupply, the NJ2013 market will start off the year with between 60,000 – 88,600 MWhs already issued and eligible to meet the 2013 requirements. Note, this assumes the September figures and October estimates provided by the NJ OCE are accurate and do not take into consideration any additional capacity to be installed in the remaining months of the 2012 compliance period.

Assembly Bill 4226

Introduced on November 10, 2011, Assembly Bill 4226, sponsored by Assemblyman Upendra Chivakula (District 17), and Assemblyman Daniel Benson (District 14), would implement changes to the current solar RPS requirements. Under the current RPS, the SREC requirements are subject to a 20% increase per year through 2027 should the state meet or exceed its solar requirements three years in a row, while also experiencing a decline in SREC pricing in those same three consecutive periods. The final paragraph of the current format of 4226, states that the 3 year time period would be reduced to 1 year and be applied beginning in the 2013 compliance period.

Should this bill be signed into law, the 20% increase would take effect in 2013. Currently, RY2013 has a requirement of 596,000 MWhs. A 20% increase would adjust the 2013 requirement to 715,200 MWh; equal to an additional 119,200 SRECs required or approximately 99.3 MW operational all year long.

Other solar trade and advocacy groups have actively suggested alternative proposals to the legislation, some of which include a revised SREC requirement schedule as well as a fixed SACP schedule through 2027. We will continue to keep a close eye on the legislative process and provide updates as more information is known and how it will impact RY2013 and future NJ compliance periods.

*This figure uses a PVWatts calculation assuming 1.2 MWh/kW/Year and takes into consideration seasonality for the remaining months left in the compliance period.